5. Commissioning

Commissioning

5.1 

Configuring Battery System

The DIP switch is used to configure the communication between battery module(s)

and the inverter. Detailed configuration information is detailed as follows:

0

1

2

3

4

5

6 7

Configuration activated by inverter

0-  Matching one battery module (default)

1-  Matching two battery modules

2-  Matching three battery modules

Black-start Configuration

The black-start function is only used in an off-grid application and when there is no 

other power supply. 
If the battery is started in the black-start mode, even when there is no BMS 

communication, the port still contains high voltage with risk of electric shock.  

After the black-start mode has started, if the BMS communication has still not been 

established within 3 minutes, the black start has failed.

 

4-  Matching one battery module 

5-  Matching two battery modules

6-  Matching three battery modules

5. Commissioning

5.2 

 Commissioning

Verify the model number of each battery module to ensure that

they are all

the  

same model. 

Once all battery module(s) are installed, follow these steps for beginning operation:

1) Configure the DIP (VI) to the corresponding number according to the number of 

battery module(s) that has (have) been installed

2) Remove the cover board of the

BMS

3) Move the circuit breaker switch (V) to the

ON position

+

4) Press the POWER button (VI) to turn on the Q.HOME  BAT-G1 system

5) Re-install the cover board to the

BMS

6) Turn on the inverter AC switch

3

4

2

NOTE!

When powering on the BMS, the system will start self-testing. If the buzzer 

beeps, it means the DIP configuration is in fault or communication failure has 

occured.

If the buzzer beeps check if the number of battery modules are 

corresponding to the DIP configuration, and also check if the RS485 

communication cables are correctly connected. After checking that these two   

situations are set, press the POWER button to power on, and press the POWER  

button again 10 seconds later. In addition, the buzzer will only sound on the  

corresponding fault during the power-on self-test. After the self-test has already

been completed, it will not beep again even if the same fault occurs.

NOTE!
Frequently pressing the POWER button may cause a system error. 

Allow at least 10 seconds after pressing the POWER button prior  

to making another attempt.

INSTALLATION AND OPERATION MANUAL LITHIUM-ION BATTERY – Q CELLS

INSTALLATION AND OPERATION MANUAL LITHIUM-ION BATTERY – Q CELLS

Summary of Contents for Q.HOME ESS HYB-G1

Page 1: ...Q HOME ESS HYB G1 Lithium Battery Series 45Ah 63Ah Valid for North America INSTALLATION AND OPERATION MANUAL Hanwha Q CELLS America Inc 614 00447 01...

Page 2: ...LLER 3 PRODUCT INTRODUCTION 3 1 PRODUCT OVERVIEW 3 1 1 DIMENSIONS AND WEIGHT 3 1 2 APPEARANCE 3 2 BASIC FEATURES 3 2 1 FEATURES 3 2 2 CERTIFICATIONS 3 3 SPECIFICATIONS 3 3 1 Q HOME BAT G1 CONFIGURATIO...

Page 3: ...SIONING 5 1 CONFIGURING BATTERY SYSTEM 5 2 COMMISSIONING 5 3 STATUS INDICATORS 5 3 1 BMS Master Box 5 3 2 BATTERY MODULE BAT45 BAT63 5 4 SHUTTING DOWN Q HOME BAT G1 SYSTEM 6 TROUBLESHOOTING 6 1 TROUBL...

Page 4: ...ON AND OPERATION MANUAL LITHIUM ION BATTERY Q CELLS Observe the following precautions Risks of explosion Risks of fire Do not subject the battery module to heavy impacts Do not crush or puncture the b...

Page 5: ...wet or submerged in water do not try to access it If the battery module seems to be damaged it is not fit for use and may pose a danger to people or property Please pack the battery in its original pa...

Page 6: ...fore performing installation 3 1 1 Dimensions and Weight A battery management system BMS is any electronic system that manages a rechargeable battery A battery module is a type of electrical battery w...

Page 7: ...tion view of Q HOME BAT G1 Object Mark Description I II III IV V VI XPLUG RS485 I GND RS485 II YPLUG Power Connector to BMS or YPLUG of upper battery module RS485 Connector to BMS or RS485 II of upper...

Page 8: ...3 BAT12 6 BAT18 9 BMS BAT BMS G1x1 BAT BMS G1x1 BAT BMS G1x1 BAT BMS G1x1 BAT BMS G1x1 BAT BMS G1x1 Battery Module Q HOME BAT G1 4 5X1 Q HOME BAT G1 4 5X2 Q HOME BAT G1 4 5X3 Q HOME BAT G1 6 3X1 Q HO...

Page 9: ...Flat Head Screw Driver Torque Wrench Tape Measure Drill Pencil or Marker 4 4 Installation 4 4 1 Check for Transport Damage Ensure the battery is intact during and after transportation If there are vis...

Page 10: ...ty 1 1 1 1 1 1 1 1 1 1 1 1 4 10 A B C E D F G I H J K L M N Battery Module BAT45 BAT63 Quantity 1 1 1 1 5 1 2 12 1 1 2 Object A1 B1 C1 D1 E1 F1 G1 H1 I1 J1 K1 Description Power Cable between Battery M...

Page 11: ...ed to ambient air The system is cooled by natural convection If the system is entirely or partially covered or shielded it may cause the system to stop operating CAUTION CAUTION The space between batt...

Page 12: ...Connection 4 5 1 Connecting Power Cables For one battery module The color at both ends of the power cable between the BMS and battery module C is orange This cable is connected to the XPLUG which is o...

Page 13: ...er K1 unlocked until the cables are correctly connected to the YPLUG Refer to the installation diagram on the right 5 On the right side of the BMS after the charging cables refer to section 4 5 5 and...

Page 14: ...r use 3 Push the plastic button on each end of the power cable in the direction of the arrow Notes for Unplugging Power Cables Lock Cover 22 23 DANGER CAUTION Do not plug or unplug the power cables wh...

Page 15: ...I RS485II VCC_485 VCC_485 GND_485 GND_485 B2 B2 N N P P A2 A2 VCC_485_2 VCC_485_2 GND_485 GND_485 The wire order of the communication cable is as follows 1 2 3 4 5 6 7 8 1 Orange stripes on white 2 Or...

Page 16: ...ect port on both the inverter and BMS 2 Connect the negative cable B to the port on the right and the positive cable A to the port on the left 4 5 5 Connecting the Charging Cables This step details in...

Page 17: ...stem installation with terminal boxes and conduit Installers are responsible for preparing conduit according to AHJ requirements Conduit size shall be 0 5in for the smaller hole and 1 1 25in for the l...

Page 18: ...onfigure the DIP VI to the corresponding number according to the number of battery module s that has have been installed 2 Remove the cover board of the BMS 3 Move the circuit breaker switch V to the...

Page 19: ...e LED indicators flash once evey 5 seconds The following table shows the status of the BMS Capacity Status Capacity Status Charging Discharging 5 3 2 Battery Module BAT45 BAT63 5 4 Shutting Down Q HOM...

Page 20: ...protection BMS_DishargeOCP Battery discharge over current protection Warning Messages Description Troubleshooting 6 Troubleshooting BMS_TemHigh Battery over temperature BMS_TemLow Battery under temper...

Page 21: ...efects that result from the following causes Force majeure flooding lightning strike overvoltage fire thunderstorm flooding etc Improper or noncompliant use Improper installation commissioning start u...

Reviews: