Technical and Operations Manual - Installation Guidance
23
UV-O Odour Control Units
Note:
To check that all UV lamps are working it is necessary to bypass the micro-
switches on the inside top front of the UV-O 500 to enable the Front Panel to be
open when the Unit is in operation. This procedure should only be undertaken by
a qualified Purified Air engineer.
CAUTION
Appropriate PPE equipment should be worn during this check.
5.
Once the lamps have been fitted and the electrical connection completed, the Front
Panel can be closed and locked.
4.4 Installing the UV-O 1000 Unit
4.4.1 Installing the UV-O 1000 Main Chassis
Figure 2
4
- UV-O 1000 Installation Schematic
Before installation, the following points should be considered:
●
The UV-O 1000 Unit should be located in close proximity to the kitchen extract
ducting.
●
The Unit should be positioned with good access to allow for future servicing and
maintenance.
●
If the Unit is to be mounted onto a wall, the casing can be drilled to allow this.
WARNING!
If you drill the case to mount the Unit onto a wall, it is important
to make sure that the fixings used will not allow any UV light to
escape.