P Z 2 - 1 2   S k i d   M o u n t   S y s t e m s

               

Installation

 

 

 

 

 

 

 

 

 

 

INSTALLATION 

 

Place the PZ2-12 System on a flat level surface. System should be tied down using an appropriate tie-down system and may be

placed back-to-back or side-by-side.

The PZ2-12 System is to be installed as a bypass system with the entrance of the bypass being after the main pool circulation pump

but before the filter, and the exit of the bypass being after the filter/heater.

Install the pressure relief (off-gas) valve to the top of the de-gas column

Connect a 3/8” hose to the valve and run the hose to a vented location for the ozone off-gas.

Locate section of plumbing in which you choose to install the ENTRANCE leg of the bypass. Location should be in any accessible

area after the pool circulation pump, but before the filter.

Connect the INLET side of the PZ2-12 boost pump to this location.

Locate section of plumbing in which you choose to install the EXIT leg of the bypass. Location should be in any accessible area after

the filter, and heater (if equipped).

Connect the OULET, (coming out of the de-gas column), side of the bypass to this location.

Electrical Installation: Prozone PZ2-12 System is a 220/240VAC system. Do not connect system to any other voltage! Use N.E.C. or

local code grounding installation procedures for swimming pool equipment.

 

1.

2.

3.

4.

5.

6.

7.

8.

9.

WATER OUTLET

DE-GAS

COLUMN

PRESSURE RELIEF

(OFF-GAS)

VALVE

BALL VALVE

WATER INLET