![PRONAR PUV-1400 Operator'S Manual Download Page 40](http://html.mh-extra.com/html/pronar/puv-1400/puv-1400_operators-manual_1617414040.webp)
PUV-1400
SECTION 4
4.4
4.2
CHECKING TECHNICAL CONDITION
When preparing the machine for normal use, check individual elements according to
guidelines presented in table (4.1).
TABLE 4.1
TECHNICAL INSPECTION SCHEDULE
DESCRIPTION
MAINTENANCE ACTIVITIES
FREQUENCY
OF
INSPECTIONS
Technical condition of blades
and collecting strips.
Inspect visually and if necessary replace
according to section "REPLACEMENT
OF COLLECTING STRIPS"
Technical condition of slides
(option)
Check technical condition, if complete
and correctly mounted.
Technical condition of linkage
Check technical condition, if complete
and correctly mounted.
Technical condition of the
hydraulic system.
Visually inspect the technical condition
Technical condition of the
electrical controls
Visually inspect the technical condition
b
e
fo
re
b
e
g
in
n
in
g
w
o
rk
Tightening of all main nut and
bolt connections
Tightening torque values should be
according to table (5.2)
Once a week
Lubrication
Lubricate elements according to table
LUBRICATION.
According to
table (5.1)
ATTENTION!
The machine must not be used when not in working order.
Summary of Contents for PUV-1400
Page 2: ......
Page 3: ...SNOW PLOUGH PORNAR PUV 1400 MACHINE IDENTIFICATION TYPE SERIAL NUMBER ...
Page 6: ......
Page 9: ...SECTION 1 BASIC INFORMATION ...
Page 19: ...SECTION 2 SAFETY ADVICE ...
Page 28: ...PUV 1400 SECTION 2 2 10 ...
Page 29: ...SECTION 3 DESIGN AND OPERATION ...
Page 36: ...PUV 1400 SECTION 3 3 8 ...
Page 37: ...SECTION 4 CORRECT USE ...
Page 53: ...SECTION 5 MAINTENANCE ...
Page 65: ...NOTES ...
Page 66: ......