
PROBOIL.4E user & installation guide v1d
44
2.3.5 Commissioning and testing
You have finished the installation, now please take a few moments to go through the commissioning and testing process, this will
ensure the product is working correctly, safely and your customer’s satisfaction.
⚠
WARNING
:
You must not skip this section, we are not liable for any safety or performance issues as a result of
not following the step by step installation guide with due care,
DO NOT TURN ON THE BOILER UNTIL FULLY FLUSHED.
1.
Switch on mains power to the boiler but leave the display screen off (in standby mode / flashing
P
).
2.
Place the Hotkey on the front of the tap, water will now begin to purge air from the entire system.
During the purging of air in the system it is normal for the tap to spit, continue until the stream from the
centre channel of the tap aerator is continuous.
Depending on the incoming water pressure it will take apx. 4-5
minutes to fill the tank and purge the air.
⚠
After
the air is purged from the system (this takes around 3 minutes) you
must
continue to run cold water
through the tank and tap for a further minimum of a 5 minutes to flush it fully.
During the flushing period check all connections made during the installation carefully for leaks.
3.
After the flushing period is completed remove the Hotkey to stop the 98°C water.
4.
Press and hold the
“
P
“
key on the boiler screen, it should switch to the standard screen and not display any
error
“E”
codes.
5.
Press the
“+”
key on the boiler screen and set the target temperature to 98°C, the boiler will take approximately
9 minutes
to reach its
“READY”
state. Use this time to complete the checklist items in this guide.
The few first times the boiler fills and heats from a “fully cold” state it is normal that the tap may drip
slightly from the spout centre channel during heating, this will self adjust with use.
6.
After the boiler reaches its
“READY”
state repeat steps 1-2.
7.
With all tap handles in the closed position again check the installation carefully again for any leaks.
Please complete the commissioning checklist, if any questions are answered as no or below the stated acceptable threshold then
you must rectify this before concluding:
Commissioning checklist
Commissioning checklist
Commissioning checklist
Commissioning checklist::::
98°C water only flow rate is greater than 1 litre per minute
Test result (LpM):
Domestic hot water only (if applicable to tap model) flow rate is greater than 2.5 litres
per minute
Test result (LpM):
Domestic cold water only (if applicable to tap model) flow rate is greater than 2.5 litres
per minute
Test result (LpM):
Cold filtered only (if applicable to tap model) flow rate is greater than 1 litre per minute
Test result (LpM):
The boiler turns on and heats water without any reported errors on screen
YES
NO
The boiler has been flushed for 5 minutes, then boiled and flushed entirely at least
twice
YES
NO
The installation and all connections have been checked for any leaks
YES
NO
You have demonstrated to the customer how to isolate water and power if needed
YES
NO
All documentation supplied has been left for or handed over to the customer
YES
NO
All pluming connections have been adjusted to length to avoid unnecessary dead legs
and prevent accidental snagging
YES
NO
The boiler is fixed to the cabinet wall to avoid accidental tipping
YES
NO
Check valves have been installed as required by local law
YES
NO