A.  Press and hold the blue I/O button for about 3 secs. 

The I/O button light dims. 

 IMPORTANT! 
 

The blow-down valve must be opened SLOWLY, not 
in one fast stroke. 

 

B.  On the back of the unit, open the Blow-Down Valve 

lever (see figure) SLOWLY by turning the handle 
until the valve is fully opened for approx. 3 secs., 
then turn the handle back to the starting position to 
close. 

C.  Keep repeating this process until the water level 

indicator reaches the bottom of the Sight Glass. 

 

 

 

If the Blow-Down Valve is connected to blow-
down tank of drainage system, you can perform 
the blow-down at operating pressure (80 psi). If 
blowing down into a container or receptacle, wait 
until the pressure drops to 10 psi. 

 

A.  When the discharge is complete and the boiler is 

drained, ensure that the blow-down valve is closed 
completely. 

B.  Press and hold the blue I/O button for about 3 

secs. to turn the unit on. 

C.  Fill the boiler with water. 

Procedure Complete 

Daily or Weekly Clean-Up 

 

 

 IMPORTANT! 
 

This process is semi-automatic and must be 
followed exactly. Frequency of this procedure 
depends upon frequency of usage. Failure to 
comply with this procedure may void the unit 
warranty. 

Remove the four funnels from the top of the unit. 

 

 IMPORTANT! 
 

Use a standard long-handle 3.5 scrub brush head and mild 
detergent only. No other cleaning tools or detergents other 
than those supplied by Prince Castle may be used. Do NOT 
use any boiler cleaning components. 

 

 

This clean-up procedure is the last procedure to be 

performed at the end of the day. 

 

Press and hold the blue I/O button for approx. 6 secs. 
to turn the unit off. 
The I/O button light dims. 

 

Press the yellow Clean button. 
The Clean button light flashes for approx. one minute 
as the unit prepares the chambers for manual 
cleaning. 
A beep sounds and the Clean button light becomes 
steady, indicating that the chambers are ready to be 
cleaned. 

 

 

Blow-down 

Valve Lever

 

 

Printed in USA  0404 © 2004 

630-500 

Summary of Contents for 630-ROM4

Page 1: ...and or mileage Travel mileage is limited to 100 miles 200 kilometers round trip one trip warranty from an authorized service agency or its sub service agency This warranty is subject to the following exceptions conditions Use of any non genuine Prince Castle parts voids this warranty All labor shall be performed during regular work hours Overtime premium will be charged to the buyer Damage caused ...

Page 2: ...pable of withstanding 340 lbs weight of unit This unit is completely pre wired and thoroughly tested prior to shipment All wiring and hookups shall be done without opening the unit Place unit on the counter The counter must be designed to fit the size and support the weight of the unit The unit must be level to insure proper function To level the unit use only the adjustable leveling feet no shims...

Page 3: ...s indicated in the Pre Installation requirements the user must provide a circuit breaker between the main power source and the unit Refer to nameplate for rating The unit is wired and tested by the factory to operate only with a single phase power configuration with one ground for main load and circuit control To avoid severe electrical shock provide grounding in accordance with N E C requirements...

Page 4: ...g cut pasta Use only pasta recommended by Prince Castle Using other types of pasta or food may cause severe damage and void all warranties and maintenance contracts 3 4 A Remove the loading box cover allowing pasta to fall into the hopper B Place loading box cover firmly on top of loading box The long cut Pasta Dispenser is now ready for use It is recommended that you keep the hopper supplied with...

Page 5: ...thoroughly before first time use Wash trays and all strainers frequently to prevent starch accumulation Switching the Unit On 1 2 Ensure that all the previous steps were executed properly before proceeding A Visually and manually check that the Blow Down valve is closed B Check that water supply line is fully opened Verify that the on off switch on the back of the unit is in ON position When unit ...

Page 6: ...as filled the Sight Glass halfway WARNING EXPLOSION DAMAGE INJURY HAZZARD The Sight Glass indicator should NEVER rise above the full position If so immediately shut down the unit and call for repair WARNING EXPLOSION DAMAGE INJURY HAZZARD Do NOT turn either of the two red handled Sigh Glass turn valves These are used by authorized service personnel ONLY Hold the blue I O button for approx 3 secs T...

Page 7: ...omplete Daily Blow Down Procedure IMPORTANT It is extremely important to fully understand and perform these maintenance procedures This procedure should be performed with caution preferably at the end of the workday For the first few days only TWO blow downs per day are recommended to clean the inside of the boiler A daily blow down is essential maintenance for a steam generator It lengthens the l...

Page 8: ...for about 3 secs to turn the unit on C Fill the boiler with water Procedure Complete Daily or Weekly Clean Up 1 IMPORTANT This process is semi automatic and must be followed exactly Frequency of this procedure depends upon frequency of usage Failure to comply with this procedure may void the unit warranty Remove the four funnels from the top of the unit IMPORTANT Use a standard long handle 3 5 scr...

Page 9: ... start the automated cleaning cycle The top gates automatically close The chambers are flushed and rinsed and the bottoms gates are closed When the cleaning cycle is finished approx 30 secs the unit automatically shuts down 6 7 A When finished ensure that all foreign objects are removed from the chambers B Replace the funnels Slide the three dispensers forward to their normal position Ensure that ...

Reviews: