AIR 40, AIR Breeze, AIR 30, AIR X MARINE and AIR SILENT-X are trademarks of Primus Wind Power 2013 Primus Wind Power Inc.
AIR Owner’s Manual
3-CMLT-2020-A
19
Amp
Meter
User Power Center
Junction Box
Battery
Disconnect
Fuse or
Breaker
Stop
Switch
Battery Bank
Turbine Positive
Red Lead
Turbine Negative
Black Lead
Chassis
Ground
Ground Rod
AIR
Wind Turbine
Generator
Tower
Tower Ground
Turbine Ground
Green Lead
Earth Ground
Fig. 8 Single Turbine Installation
AIR WIND TURBINE WIRING OPTIONS
The recommended way to connect the turbine to your battery
bank is to wire the turbine directly to its own set of battery posts;
allowing the turbine to operate independently. The AIR turbine’s
internal
regulator will monitor the battery and maintain the charge as nec-
essary.
Figs. 8 and 9 represent typical single turbine installations. Fig. 9
includes an up-tower junction box for UL (Underwriters Laboratory)
compliance.
NOTE: Contact Primus Wind Power for more information
about this configuration.