background image

Premier Tech Aqua 

3/4 

Installation guide 

 PHT tanks CCI 

 

 

Edition: 2019-01-09 

 

3.2.

 

Step 2a 

 Installing with an anchoring system (optional)  

An  anchoring  system  can  be  installed  to  prevent  problems  should  the  water  table  temporarily  and 
exceptionally rise above the base of the tank. This option is strongly recommended, but is limited as a 
preventive measure. The water table level should never rise above the first third of the 

tank’s height.

 

 

Level  and  compact  the  material  used  for 
the base.  

 

Put  the  concrete  counterweight  in  place 
(not  included).  See  table  below  for 
required weight.  

 

Add a 20 cm (8") layer of backfill material.  

 

Level and compact the backfill material.  

 

Manoeuvre the tank using the rope on top. 

 

Put the tank in place. 

 

Install  the  retainer  straps  as  shown  (not 
included). 

 

 
 

Table 2 - 

Table showing the load of the tank’s anchoring system

 

Tank model 

Resistance/strap 

Total weight of concrete 

PHT-390 

1 000 kg 

3 400 kg 

PHT-660 

1 000 kg 

5 700 kg 

Note: Use only non-corrosive materials. 

 
 

3.3.

 

Step 2b 

 Bedding preparation and tank placing 

 

Level and compact the material used for the 
base.  

 

Handle the tank using the rope on the top. 

 

Put the tank in place.  

 

 
 

3.4.

 

Step 3 

 Connecting the tank 

 

Hook  up  the  plumbing  connections  at  the 
inlet  of  the  tank  while  filling  the  tank  with 
water. 

 

MBBR,  pumping  station  and  equalization 
tanks must be ventilated using a pipe that is 
at  least  100  mm  (4")  in  diameter  or  that  is 

connected to the dwelling’s ventilation pipe.

 

 

Reviews: