GATE CARE BEFORE AUTOMATION
Before adapting the machine to the gate, check the slip, following the instructions
below:
1st Step:
Before installing the operator, check that the gate is in good mechanical
condition, that is, opening and closing properly. Manually open the gate and note
the effort required. This effort must be minimal along the entire length of the
course.
2nd Step:
Close the gate manually and check if the effort exerted was equal to the
previous operation.
The gate must have a strong structure and, as much as possible, non-deformable.
The pulleys must have a diameter consistent with the dimensions of the gate, be
in perfect rolling condition and mounted in such a way that the leaf the gate has
stability throughout its displacement. We recommend pulleys with a minimum
diameter of 120 mm.
The pictures below represent the two types of rails and pulleys used. The system
that uses a straight section (Picture A - angle) presents greater friction and
consequently greater wear. The circular section (Picture B) allows for better gate
displacement and less friction for the operator.
3rd Step:
Check that the gate leaf does not get stuck in the opening and closing
movement. The gate’s sliding rail must be perfectly straight, level, periodically free
of any element or dirt that makes it difficult for the pulleys to slide along their
entire length, as shown in the figure below.
INSTALLATION AND FIXING OF THE
OPERATOR
Before installing the operator, remove all unnecessary cables and disable any
equipment or system connected to the electrical network.
EQUIPMENT DIMENSIONS
The perfect functioning of this equipment depends on the instructions contained
in this manual. To secure the equipment, proceed as follows:
1st Step:
Check that the floor is firm enough so that the equipment can be screwed
so that it is level. If you do not comply with the requirement, provide a concrete
base, following the guidelines below:
275 mm
450 mm
400 mm
448
mm
245 mm
PICTURE A
PICTURE B