Chapter 2

Installation

Introduction

This chapter provides unpacking, inspection, installation instructions, and recommendations for installing the
OS-1933-E3-003 Multi-Carrier Power Amplifier (MCPA) Outdoor Booster System.

•  Review this chapter prior to equipment installation.
•  Review any government and local codes applicable to this installation.
•  Read the instructions in Chapter 3 before operating the equipment.

Site Survey

Powerwave recommends that a site survey be performed prior to equipment ordering or installation to reduce
or eliminate installation and turn-on delays. Note power plant capacity, cooling, RF/AC cabling/breaker
requirements, clearances for proper cooling airflow and maintenance access. System dimensions and weights
are listed in Chapter 5, Table 5-2.

Unpacking and Inspection

Perform the steps in Table 2-1: to unpack and inspect the Outdoor System (OS).

If the equipment is damaged, a claim should be filed with the carrier when the extent of any damage is
assessed. Contact the factory for a return material authorization (RMA). Refer to Chapter 4.

Electrical Service Recommendations

The base station AC supply to each OS should have a single phase UL listed AC circuit breaker rated at least
30 amps. The AC supply also requires UL listed external surge protection rated 2500 Vpk or less for 150 to 300
VAC mains installed in accordance with Article 285 of ANSI/NFPA or applicable local codes.
Table 2-2 lists the OS AC and DC current loads.

Table 2-1:  Unpacking and Inspection Instructions

Step

Action

1

Open the containers and carefully remove the cabinet, MCPAs, RFCUs and Rectifier Modules

2

Visually inspect the outdoor system for shipping damage. Check for evidence of water damage, 

bent or warped chassis, loose screws or nuts, or extraneous packing material in connectors. 

Inspect the equipment in the presence of the delivery person if possible

3

Retain all packing material that can be reused to return components to the factory

Table 2-2  Averaged AC and DC Current Loads

Number of
MCPAs

AC Current 
Max at 180 
VAC

DC Current
(max)

DC Current 
(Typical)

AC Current 
(Typical) 
@ 220 VAC

1

9.0 amps

49 amps

46 amps

6.9 amps

2

16.2 amps

88 amps

82 amps

12.3 amps

3

23.7 amps

127 amps

113 amps

17.7 amps

Summary of Contents for OS-1933-E0-003

Page 1: ...044 05243 Rev A June 2008 O U T D O O R B O O S T E R S Y S T E M I N S T A L L A T I O N A N D S E R V I C E M A N U A L OS MCPA OUTDOOR SYSTEM OS 1933 E0 003 Installation and...

Page 2: ...in this document may cause 1 Spurious emissions that violate regulatory requirements 2 The equipment to be automatically removed from service when maximum thresholds are exceeded 3 The equipment to no...

Page 3: ...OS 1933 E3 003 Revision Record 044 05243 Rev A i Revision Record Revision Date of Change Reason for Change Rev A June 2008 Initial Release...

Page 4: ...OS 1933 E3 003 Revision Record ii 044 05243 Rev A This page intentionally left blank...

Page 5: ...tial exists for equipment damage or loss of data NOTE Notes contain helpful suggestions or references to material not covered in the document Safety Any personnel involved in installation operation or...

Page 6: ...Safety OS 1933 E3 003 viii 044 05243 Rev A This page intentionally left blank...

Page 7: ...nstallation Instructions 2 2 AC Power 2 3 RF Cable 2 4 Form C Alarms 2 6 External Alarms EA 2 7 MCPA 2 7 Power system Installation 2 9 RFCU Installation 2 9 Chapter 3 Operation Introduction 3 1 Initia...

Page 8: ...arm Inputs 3 18 Chapter 4 Maintenance Introduction 4 1 Periodic Maintenance 4 1 Cleaning Air Inlets Outlets Filter 4 1 Troubleshooting 4 2 MCPA does not have a solid green LED 4 2 Rectifier Module wit...

Page 9: ...alog Box 3 4 3 4 Internet Protocol TCP IP Properties 3 4 3 5 Setting the IP Address 3 5 3 6 Enable the Connection 3 5 3 7 Rectifier Front Panel 3 8 3 8 MCPA Front Panel 3 9 3 9 Controller Module 3 10...

Page 10: ...ifier Modules 3 6 3 5 Activate TMA Channels 3 6 3 6 Adjust LNA Gain 3 7 3 7 Adjust Tx Gain 3 7 3 8 Adjust VSWR Alarm 3 7 3 9 Activate External Alarm Inputs 3 7 3 10 Status Verification 3 8 3 11 Rectif...

Page 11: ...a secure fixed location RF connections are located on the interface bulkhead plate at the bottom rear of the cabinet External power communications and alarm cables are routed through access holes loca...

Page 12: ...air through a filter mounted in the front panel vents and send heated air out the filter mounted in the rear panel The variable speed fans are dependant on the MCPA power system Controller Module tem...

Page 13: ...dule Display X Form C Fan XX Fault FT front RT frear Minor RFCU Fault 3 Sector 1 3 Critical Bypassx DC Fault 3 Sector 1 3 Critical LNA 1 Fault LNA 2 Fault Sector 1 3 Major 1 Rect Comm Fault Minor Rect...

Page 14: ...nuator Section RFCU_Sector_2 SECTOR_0 RF Interface SECTOR_1 RF Interface SECTOR_2 RF Interface BTS TX3 BTS TX4 BTS TX1 RXm BTS TX2 RXd ANT RXd ANT TX RXm VSWR BTS TX3 BTS TX4 BTS TX1 RXm BTS TX2 RXd A...

Page 15: ...n Figure 1 4 Outdoor System Rear View Door Open Power System MCPAs Controller Module Intrusion Alarm Switch Fan RF Conditioning Unit s Rectifier Modules RF Input and Output Interface Ground Power Alar...

Page 16: ...OS 1933 E3 003 Scope of Manual 1 6 044 05243 Rev A Figure 1 5 MCPA Figure 1 6 RF Conditioning Unit Figure 1 7 Control Module Front Panel Front Rear Rear Front...

Page 17: ...Scope of Manual OS 1933 E3 003 044 05243 Rev A 1 7 Figure 1 8 Power System Rectifier 0 Rectifier 1 Rectifier 2 Rectifier 3...

Page 18: ...OS 1933 E3 003 Scope of Manual 1 8 044 05243 Rev A This page intentionally left blank...

Page 19: ...factory for a return material authorization RMA Refer to Chapter 4 Electrical Service Recommendations The base station AC supply to each OS should have a single phase UL listed AC circuit breaker rate...

Page 20: ...d on the left side facing unit to allow for door swing Recommended minimum clearances for the front of the cabinet is 36 inches and 20 inches for the rear of the cabinet Refer to Tables 2 3 and 2 4 re...

Page 21: ...es Digital volt ohm meter Verify voltage Roto hammer Mounting unistrut or cabinet 10 mm hex socket wrench or nut driver Open door latches Drill bit Mounting unistrut or cabinet Screwdriver slotted 5 m...

Page 22: ...rements detailed in Chapter 5 CAUTION Prior to connecting BTS cables verify booster system power is off NOTE Do not install weatherproofing materials to cables until the booster commissioning is compl...

Page 23: ...allation Instructions OS 1933 E3 003 044 05243 Rev A 2 5 Figure 2 2 Interface Bulkhead RFCU Connections Figure 2 3 Controller Module Installation Ground Studs M8 Studs 3 4 19 mm Control Module Thumbsc...

Page 24: ...structed in Table 2 7 Alarm 1 Minor Any cabinet fan fault intrusion or rectifier communication fault The system requires attention Alarm 2 Major The system performance is degraded Alarm 3 Critical 1 S...

Page 25: ...y empty MCPA or RFCU slots before operation of the OS to prevent overheating and ensure proper system airflow Table 2 8 Form C Alarm Terminal Block Relay Connections and Conditions Relay Continuity Me...

Page 26: ...erify MCPA top and bottom quarter turn fasteners are in unlocked position as shown in Figure 2 5 4 Gently slide MCPA into subrack until seated Turn top and bottom quarter turn fasteners clockwise to s...

Page 27: ...brack may cause the pins on the D Sub connector to become recessed or broken Table 2 11 Rectifier Module Configurations Active sectors Max DC Power Number of Rectifier Modules Required Power System Ca...

Page 28: ...OS 1933 E3 003 Installation Instructions 2 10 044 05243 Rev A This page intentionally left blank...

Page 29: ...led at least one cabinet door must be closed and secured to provide adequate cooling All three OS system slots must be populated with an MCPA Rectifier or a blank panel to provide adequate cooling air...

Page 30: ...display a solid green LED If not a solid green reference the troubleshooting section in Chapter 4 11 The LEDs on the front panel of the controller will illuminate solid green for the enabled and funct...

Page 31: ...Controller Module Connections Figure 3 2 Network Connections Dialog Box Powerwave Product 192 168 255 1 Customer BTS Equipment Site LAN Local LAN Ethernet Laptop 192 168 255 2 Ethernet Typical product...

Page 32: ...OS 1933 E3 003 OS System Configuration 3 4 044 05243 Rev A Figure 3 3 Local Area Connection Properties Dialog Box Figure 3 4 Internet Protocol TCP IP Properties...

Page 33: ...3 Activate Sectors Step Action 1 Select the System Configuration Page See Figure 3 15 2 Using the pull down menus in the Installed section choose YES for the Sectors to be utilized The Sectors are 1 f...

Reviews: