32
Powerware 9350 Series 685 and 1085 Auxiliary Battery Cabinets
Installation Manual
164201408
Rev. P00 053002
Installation Checklist for Powerware 9350---160
-
All packing materials and restraints have been removed from each cabinet.
-
Each cabinet in the battery system is placed in its correct location.
-
All battery cabinets are bolted together.
-
A ground wire is installed between all cabinets that are bolted together.
-
All conduits and cables are properly routed to the battery cabinets.
-
A ground conductor is properly installed.
-
Battery cables and harness are terminated on the battery terminals E4 and E5 in the
UPS cabinet.
-
Internal battery cabinet connections have been completed (bus bars, plugs, etc.)
-
Air conditioning equipment is installed and operating correctly.
-
The area around the installed battery system is clean and dust-free.
(It is recommended that the battery cabinet be installed on a sealed concrete pad or a
sealed concrete floor.)
-
Adequate working area exists around the battery cabinet and other cabinets.
-
Adequate lighting is provided around all battery cabinet equipment.
-
A remote battery disconnect control is mounted in its installed location and its wiring is
terminated inside the battery cabinet (OPTIONAL).