Fig. 30
g. Re-fit the water governor.
h. Re-connect the burner supply pipe.
i. Test for gas soundness as follows:-
- Ensure the water service cock is in the OFF position, this will ensure that water CANNOT
flow and open the automatic valve.
- Turn ON the gas, purge and light the pilot, this will pressurise the burner supply pipe.
- Test the burner supply pipe joints for gas soundness using leak detection fluid.
j. Re-assemble remaining parts and ensure the water service cock is in the ON position.
IMPORTANT: If the automatic valve and burner manifold complete is dismantled, it can
only be tested for gas soundness under pressure AFTER blanking off all the injectors.
Fig. 31