17
PART 2 - INSTALLATION MANUAL
2.1. TRANSPORT
The bath should only be transported in the original manufacturer's packaging! After unpacking, the
bath can be carried by the aluminum frame or acrylic elements. The pipes and cables must not be
used as handles/grips!!!
2.2. SITE PREPARATION
The SPA MARINA portable bath may be operated both indoors and outdoors. The site for the bath
should comply with the following conditions:
a. the proper area and the proper transportation routes (in case of closed premises)
b. 4.5 kW ~230V (3x2.5mm
2
20A) electric connection protected by a circuit breaker switch with a
maximum cut-off value 30mA.
c. water supply and drainage (ø50)
d. leveled fl oor (fl oor drain recommended)
e. suffi cient ventilation (indoors)
f) in case of a bath installed in a closed premise, access to the electrical equipment must be pro-
vided for maintenance or inspection purposes.
2.3. BATH POSITIONING
The fl oor should be very well leveled. All the bath
legs should be on a solid and hard surface. The
total weight of the bath with water is about 750kg.
The weight of the bath should be equally spread
over the 9 bath legs. The fi gure below shows the
points of support.
Location of the bath points of support
2.4. PREPARATION OF WATER AND ELECTRICAL CONNECTIONS
Present regulations and the fact that the SPA MARINA devices are constantly powered make it
necessary to install a power line made from three wires (phase, neutral and ground) with a suitable
manual switch in the site’s electric installation. The line should be connected with the automatic cir-
cuit breaker with a maximum sensitivity 30mA.
BATH FILLING AND DRAINAGE
The bath requires connections to the water supply and sewage drain. It is equipped with a ½ ‘’ joint
that serves to transport water when fi lling and draining the bath.
It is not possible to drain the entire water content inside the bath
just through the drain valve (in the right hand side). The area
that cannot be drained is marked on the fi gure. The water there
should be removed manually (e.g. with a small bucket). The bath
should be switched off after it has been drained.