Installing Roof Poly on FieldPro with Roll-Up Side Curtain

Poly Droop

Wiggle Wire

Installed

Worker #1 

Tensioning the Poly 

Detail 1

Worker #2 

Installing the

Wiggle Wire

1st piece of

Wiggle Wire 

Second 12" Wiggle Wire 
piece to be flipped.

Detail 2

Temporary Wiggle Wire

Work this section first

4

3

7

1

1

Note:  These instructions are for a FieldPro that will feature the Roll-Up Poly Curtain. 
See page 33 for the Ground-to-Ground Roof Poly Installation.

2

3

4

5

Once the Poly is in position, place a couple of temporary sections 
of Wiggle Wire between Point  

4  

and Point 

6   

to help prevent 

the Poly from shifting while the Wiggle Wire is installed on the 
first side. 

Begin installing Wiggle Wire at Point   

2  

(center of the FieldPro) 

and work down to Point  

1  

. Return to Point  

2  

and install 

Wiggle Wire to Point  

3  

. Be sure to let the Poly edge 

overhang 3 to 6 inches. 

It helps to have two workers install the Wiggle Wire 
to prevent drooping and main proper tension down the 
entire length. One worker tensions the Poly while the 
second worker follows along inserting the Wiggle Wire
Using a helper in this manner while installing the Wiggle Wire 
will make the wrinkles disappear. See Detail 1.

Now go to the other side of the FieldPro. Begin Installing Wiggle 
Wire 
at Point  

5  

working one side at a time same as the first side. 

Use a helper again to help tension the Poly as the Wiggle Wire 
is inserted.

Be sure the Wiggle Wire is seated properly into the Wiggle Wire 
Base
. Adjust the Poly and Wiggle Wire as required.

Starting at the top of the End Frame at Point  

7  

, begin installing 

Wiggle Wire down to Point  

4  

. Go back to top and install Wiggle 

Wire down to Point  

1  

. Next do the same on the other End Frame 

of the FieldPro.

After all the Wiggle Wire has been installed on both sides and 
along the top of both End Frames of the FieldPro, the corners 
(see red dots in illustration) need to be reinforced with additional 
12" pieces of Wiggle Wire. Also note Detail 2 showing proper way 
to install the Wiggle Wire at the corners. 

6

2

5

Summary of Contents for FieldPro Gothic High Tunnel 30

Page 1: ...1 Installation Instructions PO Box 458 27725 Danville Ave Castle Rock MN 55010 poly tex com U S Canada Toll Free 800 852 3443 651 463 7009 fax 651 463 2479 Rev AJ 210121...

Page 2: ...10 Ground Stake installation Options 11 Ground Stake and Ground Stand Installation 12 Ground Stake Installation in Concrete Pier 13 Building Side Sub Assembly 14 Building Main Frame Sections 15 Erecti...

Page 3: ...using ropes or lifts If installer is not confident to erect the structure Poly Tex suggests hiring a general contractor carpenter or similar licensed business familiar with construction to assemble an...

Page 4: ...for structural failure or any legal action taken by governing agencies against purchases of non code compliance structures Failure to comply with proper installation or any modifications to the produc...

Page 5: ...traight Side Diagonal Brace Flat Bracket Corner Bracket 2 U Clamp Wiggle Wire Channel Peak Brace L Bracket All Lumber by others Middle Section Truss Purlin Purlin Cross Connector Peak Section Peak Bra...

Page 6: ...7 HT Peak Section Gothic 30 HP3506 Diagonal Brace 78 6 ft spacing GS2400 Ground Stake HP3505 Diagonal Brace 58 4 ft spacing HP3548 HT Middle Section Gothic 30 HP3503 HT Peak Brace 111 HP3340 9 8 Truss...

Page 7: ...eed Hook 2 NB1832 5 16 X 1 1 4 Carriage Bolt NB1862 Lock Washer NB1872 5 16 Hex Nut FT2057 2 U Clamp FT2106 R F End Strap HT1001 1 66 Driving Tool BMS1130 18 Spike FT2118 Spike Anchor Bracket NB1864 3...

Page 8: ...T2521 10 Bungee Ball RC1007 Roll Up Tube Bottom 6 2 1 4 RC1026 Roll Up Tube Bottom Extension 5 RC1303 U Joint w Bolts RC1314 Roll Up Crank 60 RC1316 Roll Up Door Cradle WIGGLWIRE 43 000 Wiggle Wire WW...

Page 9: ...m Stake 3 to Stake 4 Make sure all lines are level Note It is very important to accurately layout the building outline It helps to have someone assist you with laying out the building location 1 Drive...

Page 10: ...10 Layout of Ground Support Locations 4 0 Typical 6 0 Alternate Use corner to corner dimensions to verify square layout...

Page 11: ...oil and Wind Conditions Ground Stake in Concrete Pier Option 3 Special Soil and Wind Conditions Per Local Codes Ground Stake GS2400 Ground Stand GS2401 Ground Stake GS2400 See page 9 for the Ground St...

Page 12: ...nd using the Driving Tool HT1001 until the top of the ground stake is 12 above the soil line A masons twisted line is attached between all four corner stakes 8 from the top of stakes Use a line level...

Page 13: ...Place a mark 6 from top of stake Install 1 self drilling screw in the stake NB1809 1 4 14x1 Self Drilling Screw Steps Ground stakes are set into concrete so that the top of each stake is 12 above the...

Page 14: ...traight Side HP3546 into the Mid Section HP3548 See Detail A Secure frame sections together using two 2 1 4 14 X 1 Self drilling Screws NB1809 installed at each connection See Detail B CAUTION Do not...

Page 15: ...Choose a flat surface when assembling these components to ensure that all parts are in alignment Insert each Side Assembly into Peak Section HP3547 Secure frame sections together using two 2 1 4 14 X...

Page 16: ...1 Detail A Frame 3 Frame 2 End Frame Slide first three frame sections over the ground stakes until they rest on the leveling screws previously installed in each ground stake Use temporary wood bracing...

Page 17: ...peated to attach Diagonal and Peak Braces to the other end of the structure Important Make sure screws and ends of carriage bolts do not face outwards to avoid damage to poly covering All components a...

Page 18: ...sure the non swaged end faces outward and is flush with the End Frame Secure the Purlin to the End Frame using the Purlin Fastener KH1000 and 1 4 14 X 1 Self drilling Screws NB1809 See View A Insert R...

Page 19: ...A on previous page Check that each frame is plumb before you proceed to the next frame Use a 1 4 14 X 1 Self drilling Screw NB1809 at each splice See Detail A After you install the last Purlin on each...

Page 20: ...e End Strap FT2106 onto the threaded end of the Stop Tab and attach with 5 16 Hex Nut NB1872 and 5 16 Lock Washer NB1862 See Detail A Secure the End Strap to the underside of the End Frame with a 1 4...

Page 21: ...hardware See Detail A below After the last Peak Purlin section has been installed trim the Purlin end flush with the End Frame Fasten the end of the Purlin to the End Frame using same End Strap and h...

Page 22: ...ace s HY2027 can be held in place temporarily with a self drilling screw See Detail A This will keep the lower Band Braces in place until the Chord has been installed as detailed on page 23 1 5 Both S...

Page 23: ...NB1874 3 8 Hex Nut Detail A Truss Frame Assembly Attaching Truss Chords Struts Assemble the Chord Sections on a flat surface Make sure that the tabs on each end are facing the same direction Secure th...

Page 24: ...ce of 2 x 4 or 2 x 6 material for other rail locations Perimeter distance plus 10 12 lengths minimum Additional 10 lengths of treated material required Two pieces for the ller boards and three for eac...

Page 25: ...Screws NB1807 1 1 2 Lag Screw NB1810 U Clamp FT2057 3 8 X 3 Carriage Bolt NB1841 3 8 Lock Washer NB1864 3 8 Hex Nut NB1874 L Bracket FT1990 L Bracket FT1990 Corner Bracket DR7032 50 U Bracket HY2026...

Page 26: ...the Wiggle Wire Base over the top of the Peak Purlin See Detail A The Wiggle Wire Base is to be installed as one continuous run from one side of the End Wall to the bottom of the opposite side Sectio...

Page 27: ...einforce the corners after all the Wiggle Wire is installed Begin to install the Wiggle Wire all around the End Frame and across the Lower Wood Rail Note See page 30 for instructions on how to retain...

Page 28: ...tom Wood Base Rail flush with the top Section B B shows proper screw usage Attach Wiggle Wire Base to both side of vertical jambs and across bottom of header Install Wiggle Wire Base to End Frame star...

Page 29: ...es can be reused to reinforce the corners after all the Wiggle Wire is installed Install Wiggle Wire all around the End Frame across the Lower Wood Rail and around door opening Note See page 30 for in...

Page 30: ...Poly Film under a constant tension to avoid wrinkles Insert one end of the Wiggle Wire as shown above while maintaing tension on the Poly Film Bend the Wiggle Wire up just enough to clear the edge of...

Page 31: ...ladders so that the workers can easily reach the peak of the FieldPro with the Poly Use of scaffolding is highly recommended for maximum safety General Notes These instructions pertain to both Roof P...

Page 32: ...ire to prevent drooping and main proper tension down the entire length One worker tensions the Poly while the second worker follows along inserting the Wiggle Wire Using a helper in this manner while...

Page 33: ...ensions the Poly while the second worker follows along inserting the Wiggle Wire Using a helper in this manner while installing the Wiggle Wire will make the wrinkles disappear See Detail 1 Now go to...

Page 34: ...are attached at the corners Attach Cradles RC1316 to the bottom rails adjacent to the metal jambs as shown in Detail C wood side rail material by others 1 2 Note Make sure hole in jamb is oriented to...

Page 35: ...oodtite Screws NB1807 every 12 Attach Wiggle Wire Base to metal jamb pieces and header using 1 4 14 X 1 Self drilling Screws NB1809 every 12 Install the Poly material to the end wall before you procee...

Page 36: ...and tighten Install a Ball Knob on threaded ends Loop the Bungee Cords over the Ball Knobs See Detail 2 Install U Joint RC1303 onto the end of the Roll Up Tube using a 5 16 x 1 3 4 hex bolt and lock...

Page 37: ...of Poly to use for the Corner Poly Panel Use Wiggle Wire to secure this panel in place The Roll Up Poly Curtain ends should be kept just inside the End Frames The top should extend 2 above the top of...

Page 38: ...e together with 1 4 14 x 1 Self Drilling Screws See Detail A Trim the last Roll Up Tube flush with the other End Frame Use the marks previously placed on the Poly Curtain to align Roll Up Tube s See D...

Page 39: ...will be installed over the Wiggle Wire Base above Center the Brackets and use Woodtite Screws to fasten the Brackets to the upper side rails Drive the screws through the Wiggle Wire Base material See...