supply & load cable connections 

 

 

DBC1205 Installation Manual Rev J.docx   

5

 

 

 

 
 

 
 
 

Supply Cables 

The  supply  input  terminals  are  located  toward 
the  top  of  the  enclosure  and  consist  of  Earth, 
Neutral and 3 Phases, which will accept up to 
10mm

2

 cables.  The supply cables should have 

a  capacity  of  20A  per  phase,  to  allow  the 
device to be loaded to its maximum capacity. 
 

Load Cables 

Load cables can be terminated on the 12-way 
Load  and  neutral  terminal  strip  (one  for  each 
channel),  and  an  Earth  link  located  at  the 
centre of the enclosure.  These connectors will 
accept up to 6mm

2

 cables.  

It is important that 

an  individual  output  circuit  is  not  overloaded

.  

Calculate the intended load, and ensure that it 
is below the maximum capacity of an individual 
channel,  which  is  5A.    To  ensure  compliance 
with  interference  standards,  the  load  neutral 
cables  must  be  individually  connected  to  the 
neutral link terminals inside the cabinet.  

Never 

use a common neutral at a remote location

 

Load Control Cables 

Load control cables can be terminated on the 2 
x 12 way terminal strips located directly above 
the  load  terminals.    The  left  terminal  block  is 
the  output  for  1-10V,  or  DSI  if  selected  by 
software  setup.    Note  that  most  1-10V  HF 
fluorescent  ballast  control  wiring  is  polarity 
conscious.    The  +terminal  of  the  ballast 
connects  to  the  left  terminal  block,  and  the 

terminal  connects  to  the  right  (common) 
terminal  block.    DSI  ballasts  are  not  polarity 
conscious. 
 
 

Energising the Device 

If  it  is  necessary  to  energise  load  circuits 
before  any  control  cables  are  connected,  it  is 
acceptable  to  replace  the  cover  and  energise 
the  device  immediately,  as  the  default  factory 
programming  is  to  have  all  channels  set  to 
100% output.  If there is no output on any or all 
channels,  see  the  troubleshooting  section 
(page 10).  This device should be de-energised 
before terminating the control and data cables.

  

 

 

 

 

 

 

 

 

 

 

 

 
 
 
 

 

Summary of Contents for Dynalite DBC1205

Page 1: ...ynalite info philips com ABN 33 097 246 921 Philips com dynalite DBC1205 12 x 5A HF Ballast Controller Installation Manual Contents Warning 2 Hardware Controls 7 Features 2 Troubleshooting 8 Important Safeguards 2 Specification 8 Internal View 3 Mounting 4 Supply Load Cable Connections 5 Connecting Serial Control Cables 6 ...

Page 2: ...r for details Check Connections Treat this device as a switchboard that has been shipped Tighten all load carrying screw connections as vibrations from transport can cause MCB and terminal block screws to become loose Power Sources This device should only be operated from the type of supply specified on the front panel This device must be earthed Output Circuits The load on a circuit should not ex...

Page 3: ...internal view DBC1205 Installation Manual Rev J docx 3 For spare parts please call your nearest Dynalite Customer Service Centre and specify DBC1205 ...

Page 4: ... brackets are designed to accommodate 4 fixing screws up to 8mm diameter The DBC1205 can be fixed to the wall without opening the cabinet or removing covers Make sure no dust or other debris enters the device during installation Do not leave the front cover off for any length of time Excessive dust and dirt can degrade the cooling of the internal components Allow for Cable Entry Supply and load ca...

Page 5: ... must be individually connected to the neutral link terminals inside the cabinet Never use a common neutral at a remote location Load Control Cables Load control cables can be terminated on the 2 x 12 way terminal strips located directly above the load terminals The left terminal block is the output for 1 10V or DSI if selected by software setup Note that most 1 10V HF fluorescent ballast control ...

Page 6: ... for GND one pair paralleled for VE and one pair used for DATA and DATA Recommended Cable Colour Coding Green White pair Paralleled for GND Orange White pair Paralleled for VE Blue White pair Blue for DATA White for DATA Brown White pair Spare or for Join The colour coding scheme used is not critical as long as the same scheme is used throughout the installation Serial Cable Connecting Method The ...

Page 7: ...vice Switch The Service Switch has three functions 1 push Transmit Network ID 3 pushes All Channels 100 Push hold for 4 sec Reboot Top Set This adjusts the maximum output that all other control sources can select ie if the Top Set is fully clockwise 100 selected by a control source will give 100 output If it is fully anti clockwise 100 selected by a control source will give 50 output This control ...

Page 8: ... Check actual wiring against ballast manufacturer s diagram Check 1 10V DSI cable and settings specification Supply 230V 14 50 60Hz Single Phase at 60A or 230V 14 50 60Hz 3 Phase Y at 20A per phase Line Outputs 12 x Switched outputs at 5A per channel total device load 60A Control Outputs 12 x load control outputs selectable to 1 10V or DSI Protection 3 x 20A 6kA single pole thermal magnetic circui...