Battery

Load

If Peak Load Current is >2.5 Amp

move the Load termination

from DC OUT to BATTERY terminals

Mains

O’Load

Auto
Test

Fault

Mounting:

 

The power supply is designed as a wall mounting unit and should be mounted in a clean dry 
area in such a way that natural convection between the unit and the wall and through all other 
cooling slots is not restricted in any way. 

Connectors: 

Mains (K1):

 a 3-terminal block with an integral three-pole switch for Mains wiring. 

Battery (K2):

 a 2-terminal block for Battery wiring. 

DC OUT (K3):

 a 2-terminal block to connect the load – use only if peak load current is less 

than 1A.  
Care should be taken to prevent reverse polarity connections between the power supply and 
load. 

Fault Relay (K5):

 provides clean C-NC-NO contacts rated 1A @ 24Vdc. 

Commissioning: 

It is recommended that the power supply initially be connected to the Mains without the load 
connected. The green 

Mains On

 LED should be ON. The load should then be connected to the 

power supply and run without the batteries connected. The red 

Overload

 LED should remain 

OFF. If the red overload LED turns ON, the load is too great for the power supply. If this is so, 
the batteries will recharge very slowly or not at all. With the load connected, connect the two 12V 
batteries to the power supply—take care to observe the correct polarity. 
Press the RESET switch for 1 second. The 

Autotest

 LED turns ON, indicating the 24-Hour Test 

has started. Check for any Fault conditions, and press RESET momentarily to reset the 

Autotest

 and the 

Autotest

 Timer. Future Auto Tests will occur 23 hours after the reset. 