IDS-205G Switches Quick Start Guide P/N 5500396-10  (Rev A)

                                      

                                      

 

Wiring the Terminal Block 

 

Connecting the switch to ground (optional) 

 
If your installation requires additional grounding, refer to the Hardware Installation 
Guide for information on connecting ground. 

 

Connecting power to the switch 

 
You may connect both sets of power inputs to provide redundant power. 

 

1.

 

Ensure the power source is off prior to connection.

 

2.

 

Using a pair of 12-20AWG wires, strip them both 7-8mm (5/16”).

 

3.

 

Loosen the terminal block screws and connect positive (+) / negative (-) wires in 
the +/- terminals.

 

4.

 

Tighten terminal screws (0.51Nm torque). Ensure the wires are securely fastened.

 

5.

 

Re-insert the terminal block connector if removed. Turn power on at source. 
Check LED indicators for status.

 

6.

 

Connect P2 (power source 2, beginning at Step 1.

 

 

 
For complete wiring instructions and for all Hazardous Locations and 
general safety warnings consult the Hardware Installation Guide. 
 

 
Connecting a fiber device 

 
Connect LC, SC or ST fiber cable from the device to the IDS switch.

  

 

Connecting Ethernet 

 
Connect network or devices to Ethernet ports (1-4) using Cat5/5e Ethernet cables

 

Summary of Contents for IDS-205G

Page 1: ...s intended for first time setup or for product evaluation purposes Complete details can be found in the following guides at www perle com downloads IDS 205G Hardware Installation Guide IDS Managed Switches User Guide IDS Managed Switches CLI Guide What s in the box The IDS switch Quick Start Guide this document Hardware Overview ...

Page 2: ... 7 8mm 5 16 3 Loosen the terminal block screws and connect positive negative wires in the terminals 4 Tighten terminal screws 0 51Nm torque Ensure the wires are securely fastened 5 Re insert the terminal block connector if removed Turn power on at source Check LED indicators for status 6 Connect P2 power source 2 beginning at Step 1 For complete wiring instructions and for all Hazardous Locations ...

Page 3: ...us Green blinking System booting Green solid System operating normally Green blinking fast Fast Setup mode activated Red Hardware fault or firmware load error 5 Port 5 Fiberport Link Activity Off Link down Green flashing Link and activity Green blinking slowly Port in error disable or suspend state Ethernet Port Link Speed Green and Yellow LEDs 1000 Mbps Green on Yellow off 100 Mbps Green on Yello...

Page 4: ...on is recessed in the switch a small tool such as a paper clip will be required The yellow and green LEDs on an empty RJ 45 connectors will flash rapidly to indicate where to plug in the Ethernet cable from your PC 3 Using a web browser enter to a well known webpage such as www google com you will be automatically directed to the IDS Get Started screen Note While in Fast setup mode the IDS switch ...

Reviews: