Peri UP Flex Staircase 100 with Deck UDG Instructions For Assembly And Dismantling Download Page 10

A2 Assembling the first level

A2.1 Vertical Standards UVR

PERI recommend using UVR 300 (

5

) at the

first level.

Attach UH Ledgers (

3b, 3c

) to the Rosette

on the Vertical Standards UVR (

5

), then

securely fix all wedges at UVB level using
a 500g hammer.

Place provisional Ledgers UH 100 (

3c

)

shown in red, they will be removed later.

A2.2 First level Ledgers UH

2

Ø11 

hole

Ø11 

hole

Fig.A2-1

Fig.A2-2

Other combinations of standards (e.g. UVR
200 inside with UVR 300 outside) are
structurally acceptable, but the customer
must ensure safe method of erection &
striking.

Fix UBK 250/200 (

10

) to the uppermost 

Rosette of 2 No UVR 300 (

5

) shown as 

pre-assembly.

Insert Vertical Standards UVR 300 (

5

) into 

the Base Standards UVB (

2

) ensuring 

alignment of the Ø11 holes.

7

Fig.A2-3

Fig.A2-2a

Pre-assembly

Fig.A2-2b

PERI UP Flex Staircase 100 and 125 with Deck UDG

Instructions for Assembly and Dismantling – Short lift system to SG4:15

Summary of Contents for UP Flex Staircase 100 with Deck UDG

Page 1: ...PERI UP Flex Staircase 100 and 125 with Deck UDG Instructions for Assembly and Dismantling Short lift system to NASC SG4 15 Edition 01 2019...

Page 2: ...Amendment Log Version Details Issue Date 0 First Issue Jan 2019...

Page 3: ...ase 5 A2 Assembling the first level 7 A3 Assembling additional levels 10 A4 Assembling the top level 13 A5 Anchoring 15 A6 Dismantling 17 Application A7 Base reactions 20 Page Content PERI UP Flex Sta...

Page 4: ...sional specifications Dimensions are specified in mm Other units of measurement cm are used in product descriptions Conventions Instructions are numbered in sequence 1 2 3 etc Components are labelled...

Page 5: ...DI 8a End Step UAE 125 9a Industrial Deck UDG 25x100 9b Industrial Deck UDG 25x200 9c Industrial Deck UDG 25x125 for Stair Tower 125 9d Industrial Deck UDG 25x250 for Stair Tower 125 10 Node Brace UBK...

Page 6: ...out on working areas situated above ground level The assembly and dismantling sequences describe a short lift system of work in compliance with NASC SG4 15 Preventing Falls in Scaffolding Operations 3...

Page 7: ...o 1m above a top platform level Any Ledger connected between two uprights within a completed scaffold lift Any Ledger connected between two uprights up to 1m above a top platform level Inspecting the...

Page 8: ...H 200 3b Ledgers UH 100 3c UJB 38 80 55 Yellow handle A Assembly and Dismantling A1 Assembling the base UJB 38 50 30 Red handle Fig A1 2 Fig A1 3 5 Fig A1 1 PERI UP Flex Staircase 100 and 125 with Dec...

Page 9: ...rary they will be removed later Ensure all Ledgers UH are level by adjusting the Adjustable Base Plates 1 Place Steel Decks UDG 200 9b on the Ledgers UH 100 3c as an assembly aid to check squareness F...

Page 10: ...2 11 hole 11 hole Fig A2 1 Fig A2 2 Other combinations of standards e g UVR 200 inside with UVR 300 outside are structurally acceptable but the customer must ensure safe method of erection striking Fi...

Page 11: ...d 125 with Deck UDG Instructions for Assembly and Dismantling Short lift system to SG4 15 Remove provisional red Ledger UH 250 3a and attach Stair Stringer UA 6 and UH 200 3b Fig A2 5 Install Steel De...

Page 12: ...last step 7 slightly out of the holder Horizontally position End Step UAE 8 on the last step 7 Fig A2 7d The upturned edges engage in the slits The End Step UAE 8 and the last step are wedged togethe...

Page 13: ...except for the top level repeat the following steps Fig A3 1 Pre assembly Fig A3 2a PERI UP Flex Staircase 100 and 125 with Deck UDG Instructions for Assembly and Dismantling Short lift system to SG4...

Page 14: ...cal Standards UVR 5 then securely fix all wedges at UVB level using a 500g hammer Place provisional Ledgers UH 100 3c shown in red they will be removed later Attach Horizontal Braces UBH 100 100 12b b...

Page 15: ...emble Stair Steps repeating the detailed sequence in section A2 5 A3 7 Guardrails Attach UBK 250 200 10 as intermediate guardrails and remove temporary Ledger UH 100 3c above stairs Additional lift co...

Page 16: ...ds UVR 5a then securely fix all wedges at UVB level using a 500g hammer Place provisional Ledger UH 100 3c shown in red it will be removed later 13 Fig A4 1 Fig A4 2 A4 2 Guardrail Move Steel Decks UD...

Page 17: ...tailed sequence in section A2 5 A3 7 Guardrails Attach UBK 250 200 10 as intermediate guardrails and remove temporary Ledger UH 100 3c above stairs Top lift completed Install Toeboards UPY 200 14 and...

Page 18: ...r anchors is given in PERI UP Flex Staircase 100 and 125 with Deck UDG Assembly Instructions for Standard Configuration Install anchors only in the levels which have been braced with Horizontal Braces...

Page 19: ...Wall Ties UWT 140 or scaffold tube to the wall Fix Scaffold Tubes 18 to the Wall Ties UWT 140 or scaffold tube using Swivel Couplings 17 Fig A5 3a and Fig A5 4 At the intersection point of the diagona...

Page 20: ...assembly sequence described in section A2 4 Remove highlighted Ledgers UH 200 3b and UH 100 3c Fig A6 2 Progressively move down by 1m Steel Decks UDG 200 9b on to Ledgers 100 3c once more Remove Ledg...

Page 21: ...gressively remove the stair components repeating the detailed sequence in section A6 2 Remove Decks UDG 200 9b at the top of the stair flight and move down the other Decks UDG 200 9b Remove Ledgers UH...

Page 22: ...10 progressively remove the stair components repeating the detailed sequence in section A6 2 Remove intermediate level UBK 250 200 10 l Reposition Steel Decks UDG 10 9b to position shown Fig A6 7 Remo...

Page 23: ...ng for person self weight plus small tools in accordance with BS 5975 PERI recommend that the user displays clear signage indicating the permissible limits for personnel numbers thus Table 1 Tread wid...

Page 24: ...that the user displays clear signage indicating the permissible limits for personnel numbers thus Table 2 Tread width 1 25m Tower height m Max Leg Load A Max Leg Load B Max Leg Load C Equiv No of pers...

Page 25: ...asgow G21 2QA Tel 44 0 141 553 5252 4 0 Leeds Office Suite C Tuscany Way Wakefield Europort Normanton West Yorkshire WF6 2UA Tel 44 0 1924 899 848 5 0 Chepstow Riverside Court Beaufort Park Chepstow N...

Page 26: ...UK e 01 2019 Copyright by PERI Ltd Peri Ltd Formwork Scaffolding Engineering Market Harborough Road Clifton upon Dunsmore Rugby CV23 0AN Tel 44 0 1788 861600 www peri ltd uk...

Reviews: