Rev. A 2-4-2000
P/N 471438
Upon completion of commissioning and testing the system, the installer should draw the user's attention to the
following:
1.
Give the "Users Instructions" to the householder and emphasise their responsibilities under the "Gas Safety
(Installation and Use) Regulations 1994" (as amended).
2.
Explain and demonstrate the lighting and shutdown procedures.
3.
Advise the householder on the efficient use of the system, including the use and adjustment of all system
controls.
4.
Advise the user of the precautions necessary to prevent damage to the system and to the building, in the
event of the system remaining inoperative during frost conditions.
5.
Explain the function of the boiler overheat thermostat and how to reset it. Emphasise that if cut-off persists,
the boiler should be turned off and the installer or service engineer consulted.
6.
Stress the importance of an annual service by a registered heating engineer.
7.
The electrical mains supply to the appliance must remain on for the frost protection circuit to operate.
Installation Section / Commissioning
18