Commissioning
A commissioning test involves a 25% (50% if manual) static overload test and,
as elements of the crane’s safety features may have to be overridden, it must
only be carried out by a trained and competent person.
It is a legal requirement that a commissioning test must be carried out:
-
Before being put into use for the first time.
-
If the crane is fitted to a new or modified structure.
-
After any modifications have been carried out to the crane or support
structure.
-
Following any incident which may have caused damage to the crane or
its supporting structure.
The Association of Lorry Loaders, Manufacturers and Importers, (ALLMI), also
recommend that on commissioning a 10% dynamic over-load test is conducted
by a trained and competent person through full slewing arc.
In severe or extreme conditions, it is recommended that commissioning is
incorporated into the annual load test of the crane and its supporting
structure.
Please contact Penny Hydraulics Ltd. for further information.