A. 

Install wood blocking between the top of the 

window and the soffit as shown.

 The blocking 

should be flush with the exterior of the window 
frame.

B. 

Apply a bead of sealant on the leg of the head 

frame expander

 and install by tapping on it 

using a block of wood with rounded edges and 
a hammer. Frame expander is pre-notched and 
bent from the factory.

6B

6A

6

SEALING THE WINDOW TO THE 

EXTERIOR WALL CLADDING (CONTINUED)

C. 

NEW CONSTRUCTION APPLICATIONS 

WITH SQUARE JAMB COVER

Flash 

from jambs to water resistive barrier.

  In new 

construction application, use flashing tape to 
flash from the jamb of the unit to the water 
resistive barrier.  Overlap onto the unit jamb 
at least 3/8”.  If necessary, repair any punctures 
with another piece of flashing tape

D. 

Insert backer rod.

 If required, install siding, 

then insert backer rod into the space between 
the exterior finish material and unit exterior 
deep enough to provide at least a 1/2" clearance 
between the backer rod and the exterior face of 
the wall sheathing.

Note: Backer rod adds shape and depth for the 
sealant line.

E. 

Apply a bead of high quality exterior grade 
sealant

 to the entire perimeter of the window, 

except for one inch at either side of the sill. DO 
NOT fill between the frame expander and the 
under side of the seat board.

F. 

Shape, tool and clean excess sealant.

 When 

finished the sealant should be the shape of an 
hourglass.

Note: This method creates a more flexible 
sealant line capable of expanding and 
contracting.

Installation Complete.

Exterior 

6D

6E

6C

INSTALLATION USING ANGLE JAMB COVERS:

G. 

Cut jamb covers to length.

 Measure height of one flanker unit not including 

head & seatboard. Cut jamb covers to 4-9/16” taller than flanker unit height.

H. 

Notch leg of jamb covers.

 On one jamb cover, notch the leg 3” from one end and 2” from the 

other end. Mirror these notches on the other jamb cover, to create a right and left handed part.

I. 

Install exterior jamb covers.

  Apply sealant along the leg of each jamb cover and drive this leg 

into the accessory groove using a block of wood with rounded edges and a hammer. Install the 
jamb covers with the 3” notch towards the sill.

J. 

Nail the jamb covers to the wall

 using one nail on each end and one in the center.

K. 

Cut two pieces of flashing tape

 6” longer than the jamb covers. Apply tape 3” above the top 

of the jamb cover, overlapping it onto the water resistive barrier.

If using Square Jamb Cover, Proceed to Step 6C.
If using Angle Jamb Cover, Proceed to Step 6G.

Angle Jamb Cover

Square Jamb Cover

Angle Jamb Cover

ALL

ALL

ALL

ALL

ALL

ALL

ALL

NEW

 

CONST

NEW

 

CONST

NEW

 

CONST

NEW

 

CONST

NEW

 

CONST

ALL

ALL

ALL

ALL

ALL

ALL

ALL

ALL

ALL

ALL

ALL

ALL

Summary of Contents for 81470102

Page 1: ...ion in a wall system designed to manage water These instructions are not to be used with any other construction method Installation instructions for use with other construction methods multiple units...

Page 2: ...knife Drill with a 2 Phillips at least 4 long and 3 square drive bit provided in cable clamp kit 1 2 open end wrench 3 16 wrench or socket Sealant Gun Installation will require two or more persons for...

Page 3: ...k and rough opening Apply sealant at each joint between the brick blocking and rough opening and cover the joints with flashing tape H Apply sill flashing tape 1 Wood wall construction only Cut a piec...

Page 4: ...tape 2 Cut a piece of flashing tape 12 longer than the opening width Apply at the bottom overlapping tape 1 by at least 1 DO NOT allow the tape to extend past the interior face of the opening Note The...

Page 5: ...Check window for squareness by making sure diagonal measurement for corner to corner is within 1 8 in both directions Insert a 10 x 3 flat head wood screw into each pre drilled hole in the jamb boards...

Page 6: ...etween the rafter tails directly above the cable holes in the bay bow head board B Remove the cable from the bay bow unit Measure the distance from the bottom of the cable clamp to the bottom of the h...

Page 7: ...put on the seat board knee braces must be used in addition to the cables HEAD BOARD SEAT BOARD 18 PROJECTION MAXIMUM DASHED LINES INDICATE POSSIBLE CONSTRUCTION FOR GABLE ROOF MINIMUM 10 1 2 HEADER MO...

Page 8: ...space between the window and the rough opening and apply a 1 deep bead of foam This will allow room for expansion of the foam and will minimize squeeze out If using foam other than Great Stuff Window...

Page 9: ...Foam BRICK FRAMED REPLACEMENT 3 8 Clearance Backer Rod and Sealant typical Insulating Foam BRICK SMALL BLOCK REPLACEMENT Air Gap Block 1 x 2 Sheet Rock Lathe Plaster Insulating Foam 3 8 Clearance Bac...

Page 10: ...ween the frame expander and the under side of the seat board F Shape tool and clean excess sealant When finished the sealant should be the shape of an hourglass Note This method creates a more flexibl...

Page 11: ...cess sealant When finished the sealant should be the shape of an hourglass Note Backer rod adds shape and depth for the sealant line This method creates a more flexible sealant line capable of expandi...

Page 12: ...construction and maintenance failure to install Pella products in accordance with Pella installation instructions or the use of Pella products in wall systems which do not allow for proper management...

Reviews: