A. BOILER SUPPLY AND RETURN
1. Size the supply and return to suit the system. A
typical piping arrangement is shown in Figure 3.1.
Refer also to the I=B=R Guide - Residential
Hydronic Heating Installation/Design and the PB
Heat Water Survey for additional guidance during
water piping installation.
2. Return Piping:
Pipe the drain valve to a tee, provided, and the
1-1/4 NPT return tapping near the bottom of the left
section. Pipe the return to the tee. Pipe the drain
valve nipples and tee to the 1-1/4 NPT return
tapping as shown in Figure 3.1.
3. Supply Piping:
Pipe the supply to the 1-1/2 NPT supply tapping at
the top and rear of the boiler.
4. When system return water temperature will be below
130°F (54°C), pipe the boiler with a bypass
arrangement to blend the system return and hot
supply to obtain at least 130°F (54°C) entering the
boiler. For more information on bypass piping,
consult the PB Heat Water Survey.
3. WATER PIPING AND CONTROLS
Figure 3.1: Supply and Return Piping
WATER PIPING AND CONTROLS
Summary of Contents for MI85 Series
Page 1: ...MI85 Boilers Series Gas Installation Operation Maintenance Manual...
Page 20: ...18 ELECTRICAL Figure 6 4 Wiring Diagram Intermittent Ignition 3200 Control...
Page 21: ...19 Figure 6 5 Intermittent Ignition System Operating Sequence ELECTRICAL...
Page 22: ...20 ELECTRICAL Figure 6 6 Zone Wiring with Zone Valves Figure 6 7 Zone Wiring with Circulators...
Page 24: ...22 START UP PROCEDURES Figure 7 3 Operating Instructions...
Page 25: ...23 Figure 7 4 Operating Instructions START UP PROCEDURES...
Page 36: ...34 REPAIR PARTS Figure 11 2 Manifold Figure 11 3 Gas Valve and Pilot Intermittent Ignition...
Page 38: ...36 Figure 11 4 Block Draft Hood Figure 11 5 Jacket REPAIR PARTS...
Page 40: ...38 Figure 11 6 Controls Circulator Vent Damper REPAIR PARTS...
Page 42: ...40 NOTES...