BOILER SET-UP
1. Provide a sound, level foundation. Locate boiler as
near to the chimney or outside wall as possible and
centralized with respect to the heating system.
2. Locate boiler in front of installation position before
removing crate.
3. If using combustible floor pan, position pan on
foundation or flooring.
4. Separate the wood shipping pallet from the boiler
base by removing two (2) hold-down bolts at each
end of the boiler base.
5. Move boiler into final position. If using combustible
floor pan, install boiler on pan as outlined in the
instructions included with the pan.
2. BOILER SET-UP
7
Summary of Contents for DE-03
Page 1: ...DE Boilers Series Gas Installation Operation Maintenance Manual ...
Page 26: ...START UP PROCEDURES Figure 7 3 Operating Instructions 24 ...
Page 27: ...25 Figure 7 4 Operating Instructions START UP PROCEDURES ...
Page 32: ...30 TROUBLESHOOTING Figure 8 1 Procedure For Measuring Fan Suction Pressure SEE TABLE 7 ...
Page 39: ...37 This page intentionally left blank ...
Page 42: ...40 REPAIR PARTS Figure 11 2 Base Burners Manifold ...