Planning the installation
33
Model 4520 & 4110 Series Getting Started Guide
3 • Installation
Installation checklist
The installation checklist (see
table 5
) lists the tasks for installing a SmartNode 4520 or 4110 Series router.
Make a copy of this checklist and mark the entries as you complete each task. For each SmartNode 4520 or
4110 Series router, include a copy of the completed checklist in your site log.
Table 5. Installation checklist
Task
Verified by
Date
Network information available & recorded in site log
Environmental specifications verified
Site power voltages verified
Installation site pre-power check completed
Required tools available
Additional equipment available
All printed documents available
SmartWare release & build number verified
Rack, desktop, or wall mounting of chassis completed
Initial electrical connections established
ASCII terminal attached to console port
Cable length limits verified
Initial configuration performed
Initial operation verified
Summary of Contents for SMARTNODE 4110 Series
Page 6: ...Contents Model 4520 4110 Series Getting Started Guide 6...
Page 8: ...Compliance information Model 4520 4110 Series Getting Started Guide 8...
Page 14: ...About this guide Model 4520 4110 Series Getting Started Guide 14...
Page 47: ...47 Chapter 5 Monitoring Status Chapter contents Status LEDs 48...
Page 60: ...A Specifications Model 4520 4110 Series Getting Started Guide 60 Power supply...