Good wiring practice does not permit the hard-wiring of data lines to 

end devices, such as Pathports.
To facilitate proper practice, PWPP WM P2 gateways ship with an 

in-line female RJ45 mini-jack, similar to a punchdown connector, as 

well as a short male-to-male RJ45 jumper to connect the jack to the 

node. (The jumper and jack are available as an accessory package 

for the PWPP WM P1.)
First determine if the installation is using the TIA568A or TIA568B 

wiring scheme. Strip back the outer insulation jacket of the building 

wire no more than ¾”. Untwist the pairs, trim them to the same 

length but do not remove insulation from the individual wires. Slip 

the individual wires into the clear plastic guide piece, following the 

color coding scheme on the sticker. Position the guide piece onto 

the connector half of the jack. Press down firmly or gently apply 

pressure with a pair of pliers until the two pieces click together. The 

mini-inline connector is removable, if necessary.

Disconnect all power before proceeding with the installation. If the 

Pathport has been pre-configured, check the temporary label to 

ensure the Pathport is being installed in the correct location.

PWPP WM P2s should be installed in standard two-gang masonry 

deep backboxes (ears in) for flush-mounting or, for surface mounting, 

in Pathport surface mount backboxes, part number PWACC WMP2. 

Use of other surface mount backboxes is not recommended. Check 

the backbox for obstructions or any foreign material. The backbox 

should be clean and empty of debris. Install the in-line Ethernet jack 

provided, if necessary.
Attach  the  Pathport  trim  ring  to  the  backbox  with  the  4  screws 

provided. Do not over-tighten or distort the shape of the trim ring. 
Inspect  the  Pathport  and  make  sure  all  components,  including 

the printed circuit boards, are secure. Note that it is normal to see

 

exposed metal on the mating connectors.
If the backbox contains an RJ45 female punchdown connector, 

use the male-to-male jumper (included) to connect it to the node.  

Otherwise, plug the male RJ45 pigtail directly into the connector on 

the back of the node. Attach the green ground wire to the ground 

screw in the backbox.
If local power is required for the Pathport, see the note on local 

power at the end of this guide.

Disconnect all power before proceeding 

with installation.

PWPP WM P1 single-port gateways 

are designed to be installed in standard 

masonry deep backboxes (ears in) for 

flush mounting, or deep (minimum 58mm 

or 2.25”) surface mount backboxes.
If the Pathport has been pre-configured, 

check the temporary label to ensure the 

gateway is being installed in the correct 

location.

PWPP WM P1s can be permanently set 

to a specific DMX universe, 1 through 

4,  by  use  of  a  jumper  on  the  back 

edge of the circuit board. If the system designer has not given 

specific instructions about the setting, then leave the jumper in 

the NET position, and configure standard or custom patches using 

Pathscape.
Because PWPP WM P1s do not have a front panel display, if you 

are installing multiple gateways it’s a good idea to maintain a log 

of  serial  numbers.  The  serial  numbers  are  exposed  when  the 

gateways are discovered in Pathscape which is where they will 

be patched. If the devices are easily visible from where you run 

Pathscape, use the “Identify” feature, which will blink the blue NET 

LED and the green DMX LED on the selected gateway.
Once  this  information  is  recorded,  check  the  backbox  for  

obstructions or foreign material. The backbox should be clean 

Gently insert the Pathport straight into the backbox, lifting it slightly 

so that is high in the backbox. Once all the way in, lower it until 

the tabs at the top of the trim ring take hold of the face plate. 

Once the top of the gateway’s faceplate is retained, swing the 

bottom in tight to the wall. Make sure no wiring or connectors are 

pinched, excessively bent or stressed. Using a #0 Phillips driver 

(not included), tighten the two setscrews provided, one on each 

side of the gateway’s face, to complete installation. If the Pathport 

has shipped with hex-head set screws, instead use a 1/16” Allen 

key (not provided)

The Pathport is ready to be powered up.

IN-LINE JACK INSTALLATION

PATHPORT WALL-MOUNT 2-PORT 

(PWPP WM P2)

PATHPORT WALL-MOUNT 1-PORT 

(PWPP WM P1)