background image

11

NITROGEN GENERATORS

INSTALLATION, OPERATION, AND MAINTENANCE MANUAL 

7. OPERATION

7.1 Startup

The inlet and outlet connections to the Parker Nitrogen Generator must be checked for leaks prior 
to system start-up. After the system is properly installed and checked for leaks, the inlet gate valve 
can be slowly opened to introduce compressed air to the system.
During start-up and adjustment of the system, the nitrogen produced by the system will vary in  
purity. If the application for the nitrogen is critically dependent on purity, the nitrogen produced  
during start-up or adjustment should be vented.
If the outlet nitrogen flow is closed, the system will still consume compressed air. The inlet air is  
simply vented to atmosphere through the permeate ports of the membrane module. To eliminate 
compressed air consumption if nitrogen is not required for the process, shut off the compressed  
air supply to the generator.

7.2 System Adjustment for Desired Outlet Purity

The inlet air pressure must be constant for the system to supply nitrogen of consistent purity to  
the application. The inlet pressure to the Parker Nitrogen Generator should be maximized (within 
process and generator parameters) to optimize the operation of the membrane module. The inlet  
air consumption for different operating pressures is shown in the table on page 20. Nitrogen purities 
and flow rates for different operating pressures are shown on page 12.
Flowmeter settings for a given operating pressure are shown on the Nitrogen Purity label attached  
to the front of the unit and displayed on the next page. There may be a 5 psig to 15 psig pressure  
differential between the pressure of the compressed air supply at the inlet and the operating pressure 
of the membrane module. The pressure differential observed is dependent on the outlet nitrogen flow 
rate as well as the operating pressure. This pressure loss must be taken into account when  
determining the inlet pressure which will deliver the desired purity and flow of nitrogen from  
the generator.
To adjust the pressure regulator on the front panel of the generator, pull the knob out, adjust  
the pressure and push the knob back in to lock the setting.

Summary of Contents for N2-120

Page 1: ...Nitrogen Generator Installation Operation Maintenance Manual Models N2 120 N2 160 N2 240...

Page 2: ...NITROGEN GENERATORS INSTALLATION OPERATION AND MAINTENANCE MANUAL 1...

Page 3: ...ty 11 8 NITROGEN FLOW AT GIVEN OPERATING PRESSURE AND PURITY 12 9 OPERATION ADJUSTMENT PROCEDURES 14 9 1 Atmospheric Pressure Applications 10 psig 0 7 barg 14 9 2 Elevated Pressure Applications 10 psi...

Page 4: ...of purchase when this product is operated and maintained according to the instructions provided with the product then Parker guarantees at Parker s option to replace the product repair the product or...

Page 5: ...manual and by other safety governing bodies will void the safety certification of this product Any modification of the product will void the warranty If you have any questions or concerns please call...

Page 6: ...100 psig 6 9 barg outlet pressure To achieve this outlet pressure the inlet pressure needs to be approximately 110 115 psig 7 6 7 9 barg 4 ENGINEERED SYSTEM The Parker N2 120 N2 160 and N2 240 Nitrog...

Page 7: ...er rate than nitrogen molecules This differential permeation results in a high purity dry nitrogen gas stream exiting the membrane module The oxygen enriched permeate stream is exhausted through ports...

Page 8: ...tration in a process stream It can be easily installed on top of the nitrogen generator and connected to the outlet nitrogen line using appropriate fittings 6 INSTALLATION All installation operation a...

Page 9: ...tor to up to 2 instruments and to the compressed air supply See Figure 4 for the recommended installation schematic Shutoff Valve A shutoff valve should be installed directly upstream from the nitroge...

Page 10: ...air at room temperature and relatively free of water compressor oil hydrocarbons and particulate matter An oil content 0 01 mg m3 is recommended The dewpoint of the incoming air is recommended to be l...

Page 11: ...rker Nitrogen Generator and the receiver tank see Figure 5 The Balston 72 460 V883 Back Pressure Controller contains both components and may be ordered as an accessory for the Nitrogen Generator The a...

Page 12: ...ust be constant for the system to supply nitrogen of consistent purity to the application The inlet pressure to the Parker Nitrogen Generator should be maximized within process and generator parameter...

Page 13: ...0 PSIG 100 PSIG 125 PSIG 145 PSIG Meter SLPM Meter SLPM Meter SLPM Meter SLPM Meter SLPM Meter SLPM Meter SLPM 99 50 0 7 32 0 9 43 1 1 54 1 3 66 1 5 78 1 9 110 2 1 133 99 00 1 0 43 1 2 55 1 5 71 1 7 8...

Page 14: ...r SLPM Meter SLPM Meter SLPM Meter SLPM 99 50 0 9 23 1 3 34 1 6 47 2 0 60 2 2 75 2 5 88 2 7 100 99 00 1 2 30 1 6 44 2 2 63 2 7 81 2 9 100 3 4 119 3 7 138 98 00 1 7 43 2 3 63 3 0 88 3 7 113 4 2 144 4 8...

Page 15: ...en at or near atmospheric pressure e g purging or blanketing applications use the following procedure for start up and adjustment of the system 1 Open the customer installed inlet air gate valve 2 Adj...

Page 16: ...djust the customer installed inlet air pressure regulator until the Operating Pressure gauge see Figure 1 shows the pressure required to deliver nitrogen at the desired flow rate per flowmeter adjustm...

Page 17: ...nerator to the proper reading as specified by the Flowmeter Adjustment Label 6 Purge the entire system venting the initial nitrogen stream through the vent valve to atmosphere Purge time is dependent...

Page 18: ...9 7 Shutting Down Proper shutdown of the Parker Nitrogen Generator can be accomplished by simply closing the customer supplied inlet air gate valve see Figure 4 or 5 If this valve is left open the sy...

Page 19: ...1B1 BX filter assemblies Replace these filter cartridges with Balston 100 18 DXE and 100 18 BXE filter cartridges When replacing the prefilter cartridges be sure to install the proper grade filter in...

Page 20: ...o the generator and allow the system to depressurize 2 Disconnect the upper hose from the filter using the 7 8 open end wrench 3 Remove the two lockdown knobs to release the filter 4 Disconnect the lo...

Page 21: ...essure Drop 15 psig 0 7 barg Min Max Ambient Operating Temp 34 F 140 F 1 C 60 C Recommended Ambient Operating Temp 68 F 20 C Max Relative Humidity 80 Altitude 2000 m Max Min Max Inlet Air Temp 40 F 13...

Page 22: ...is nontoxic and largely inert It can act as a simple asphyxiant by displacing oxygen in air Inhalation of nitrogen in excessive concentrations can result in uncon sciousness without any warning sympto...

Page 23: ...fied Check setting of flow rate Check the operating pressure to assure that it has not varied from the original reading Check the system for leaks Calibrate oxygen analyzer if needed Air Leak Through...

Page 24: ...410 5121 Engine Mobile Filtration Division EMEA Dewsbury United Kingdom 44 0 1924 487 037 Gas Separation Filtration Division EMEA Team Valley United Kingdom 44 0 191 402 9000 Gas Turbine Filtration Di...

Reviews: