7
1.
Remove Plaster Cap from Fountain and blow out
the lines to remove any construction debris that may
be in the pipes.
2.
Set the end of the fountain shaft with the stopper
down over the fountain body and mark the water level
on the shaft.(See Figure 17)
3.
Transfer the water level mark to the other two
shafts. (See Figure 18)
4.
Using the longest 53-inch shaft, measure and mark
an additional 13¼ inches away from the stopper end.
(See Figure 18)
5.
Using the 45-inch shaft, measure and mark an
additional 5¾ inches away from the stopper end. (See
Figure 18)
6.
Using the 40-inch shaft, measure and mark an
additional ¾ inches away from the stopper end. (See
Figure 18)
7.
Cut all three fountains at the farthest mark from the
stopper end.
8.
Insert each fountain shaft through a fountain
retainer so the bottom of the fountain retainer is next
to the stopper that is glued to the shaft. (See Figure
19)
9. Umbrella Fountain
(See Figure 20)
a. Select the longest fountain shaft.
b. Put a small dab of PVC glue on the outside of the
threaded insert and press into the shaft opposite the
stopper end.
c. Glue the umbrella end-cap over the outside of the
fountain shaft, or same end as the threaded insert.
d. Wipe off any excess glue.
e. Thread the umbrella into the threaded insert until
you have a 1/16 inch gap. When installed balance
flow and gap to desired effect.
10. Flower Fountain
(See Figure 21)
a. Select the medium length fountain shaft
FOUNTAIN STARTUP INSTRUCTIONS
:$7(5/(9(/
&87/,1(
&87/,1(
&87/,1(
67233(5
WATERLINE
MARK AT
WATER LINE
To Top Of
Fountain
Waterlevel
Cut Marks
9"
10"
11"
8"
7"
6" OR
LESS
Fig. 17
Fig. 18
Fig. 19