INSTALLATION INSTRUCTIONS CM361C

For Technical Support: www.panduit.com/resources/install_maintain.asp

Cable Routing and Slack Management

Determine the direction of the incoming and 
outgoing cables in order to select which 
entry/exit knockouts to remove. Once 
removed install the grommets from the inside 
of the enclosure. (Each grommet is designed 
to hold 48 Category 6a cables.)

NOTE: Allow a minimum of 14” of cable slack to allow the door to open and close properly.

Entry/Exit knockouts 

Page 5 of 8

Cable Routing 

Enclosure door open

Enclosure door closed

Utilizing the four back grommets requires a proper slack loop to allow the door to open and close properly. The diagrams below illustrate 
how to route the cables and where to secure the cables using a tie-down bar. The tie off point should be approximately 24” away from 
cable entering point of enclosure and 6” above the top.

Tie down bar used 
to secure cables

Secure cable at 
this location

Secure cable at 
this location

Tie down bar used 
to secure cables

Note:

  Install all cabling in accordance with NEC article 300.22 and 

article 800.

Summary of Contents for PZICEA

Page 1: ...ling Tile Template 1 Electrical Junction Box 1 Integrated Horizontal Slack Manager 1 Adjustable Air Dam 2 Filters 4 Entry Exit Knockout Plates Install in Ceiling Electrical Installation Equipment Inst...

Page 2: ...out template over the removed ceiling tile Secure the template with tape of thumb tacks Trace the outline with a utility knife to extract the necessary shape to insert into the enclosure While the enc...

Page 3: ...experienced professional to the latest local building codes and regulations Conduit Knockouts Mounting Holes Receptacles not included Mount the electrical box to the side of the enclosure Use 4 10 32...

Page 4: ...ermination box 3 RU for Patch Panels facing forward 2 RU for Network Switches Brackets mounted toward front for deepest active equipment Recommended for switches 17 5 deep Brackets mounted toward back...

Page 5: ...n and close properly Entry Exit knockouts Page 5 of 8 Cable Routing Enclosure door open Enclosure door closed Utilizing the four back grommets requires a proper slack loop to allow the door to open an...

Page 6: ...ates how cables are routed from switch to patch panels Step 1 Plug in a 3 1m patch cord into a port on the switch Route patch cord up and into the integrated horizontal slack manager Create a loop in...

Page 7: ...into the integrated horizontal slack manager Create a loop in the patch cord and bring forward Plug other end of the patch cord into the desired jack in the patch panel Repeat the process for each bay...

Page 8: ...thread cutting screws as shown 2 Remove old filter and replace with new one 3 Install filter bracket with 3 6 32 thread cutting screws 4 Repeat process on opposite side 1 Unplug fan from power source...

Reviews: