© Panduit Corp. 2019
OPERATING INSTRUCTIONS
CTFP-100
ENGLISH
PA29444A01_02_ENG
Page: 5 of 8
3-2019
3. OPERATION
3.1 ....... Commissioning
•
Check whether finger guard (1) is
present and is sitting firm.
•
Check whether the die set (2) is free
from foreign matter.
•
Check whether the pneumatic tubing
nuts (3) have been tightened firmly.
•
Introduce the table clamp (4) into the
bore hole in the tabletop unit and
screw tightly to the worktable.
•
Check the compressed-air supply:
min. 4 bar, max. 6 bar filtered air
•
Connect the free connection (5)
on the foot switch to the
compressed-air supply
Figure 2 - Commissioning
3.2 ....... Operation
•
Introduce stripped wire with wire-end
ferrules already fitted, at the side (1) in
the hole assigned to the cross-
section.
•
Press the switch (2), the crimping
process will be triggered.
•
Release the switch (3), the crimped
wire can be removed again (4).
Figure 3 - Operation