Chapter 2. Installing Pipe Nozzles
10
Model T17 Installation Guide
2.2.3 Determining and Marking the Second Nozzle Location, Diametrical (cont.)
7.
Place the strip of film on the pipe again. This time, line up the overlap mark with the horizontal and vertical scribe
lines. Again, make sure you wrap the strip of film squarely around the pipe.
8.
The new position of the center of the second nozzle is now identified as the intersection of the fold line and the
second edge of the strip of film. Center punch this location prior to removing the strip of film.
9.
Remove the film.
10.
Scribe 6” long vertical and horizontal lines that intersect at the center-punch mark.
Overlap Mark
First Edge
Side View
Fold Mark
Side View
Punch Here
Second Edge
Scribe Lines
Side View
Summary of Contents for T17
Page 2: ......
Page 4: ...ii no content intended for this page...
Page 7: ...Model T17 Installation Guide v Chapter...
Page 8: ...Chapter vi Model T17 Installation Guide no content intended for this page...
Page 10: ...Contents viii Model T17 Installation Guide...
Page 11: ...Model T17 Installation Guide ix Contents...
Page 12: ...Contents x Model T17 Installation Guide...
Page 46: ...Chapter 3 Installing an Isolation Valve 34 Model T17 Installation Guide...
Page 64: ...Chapter 4 Inserting T17 Transducers into the Pipe 52 Model T17 Installation Guide...
Page 70: ...Chapter 6 Specifications 58 Model T17 Installation Guide...
Page 72: ...Warranty 60 Model T17 Installation Guide no content intended for this page...
Page 74: ...2 Model T17 Installation Guide...
Page 75: ......