DigitalFlow™ GC868 Startup Guide (1 and 2-Channel)
1-10
Chapter 1. Installation
Based on the pipe OD, proceed to the appropriate section:
•
If the pipe < 12” (300 mm), see the section
Installing the V Series Clamping Fixture
and Transducers
on the next page.
•
If the pipe > 12” (300 mm), go to
Installing the PI Fixture and Transducers
on
page 1-12.
1.4.4
Installing the V
Series Clamping
Fixture and
Transducers
Note:
A complete installation involves the clamping fixture, transducers and
damping material. Refer to
Installing Damping Material
on page 1-17.
To install the V Series clamping fixture and transducers, complete the following
steps:
1.4.4.1
Installing the
Fixture
1.
Position the half of the clamping fixture with the threaded rods around the pipe,
as shown in Figure 1-6 below. Orient the fixture in the 3 o’clock position on a
horizontal pipe.
2.
Position the mating half of the fixture over the threaded rods in the 9 o’clock
position. Figure 1-6 below shows the two mounted halves.
Figure 1-6: Mounting the Two Halves of the Fixture
The two fixture halves have measuring scales; ensure that the scales are on the
same side of the fixture, so that both zeros start at the same origin, as shown in
Figure 1-7 below.
Figure 1-7: Fixture with Scale Origins Properly Aligned
0
1
2
3
4
0
1
2
3
4