5.3 Fitting High Speed Pumps on the iCELLis 500+ Control System
WARNING!
Risk of injury to personnel and/or damage to equipment!
The positioning of the high-speed pumps must be done by two people due to the weight of the pumps.
ALERT!
Risk of damage to equipment!
Always check the position and stability of the accessories pump before operation.
WARNING!
Risk of injury to personnel and/or damage to equipment!
Before installing the accessories pump, turn the iCELLis 500+ control system OFF, unplug the system
from the AC power, shut down gas supply, disconnect gas lines, remove the bioreactor, remove the
manifolds and all liquids.
The high-speed pumps are packed in the crate for accessories and documentation. Unpack each high
speed pump, and install the pump in its compartment (Figure 9a) prior to connecting to the iCELLis
500+ control system as per the Figure 7b. Connect the power cable (Figure 9c) and the communication
cable (Figure 9d) to the iCELLis 500+ control system. Power to the pumps is supplied by the Control
system.
Figure 9: Placing and connecting High Speed pump:
a) High speed pump compartment,
b) High speed pump in compartment, c) Connection of power plug, d) Connection of communication port.