Step 10. Complete Lower Cable Installation
1 - 3½" pulley
1 - 2" bolt
2 - washers
1 - locknut
C
1 - 3½" pulley
1 - 2" bolt
2 - washers
1 - locknut
A
1 - 4½" pulley
1 - 2¼" bolt
2 - washers
1 - locknut
D
Floating Pulley
Plates
Floating
Pulley
Plates
Pulley Support
Tube
Plates at the Base of
the Main Upright
10. Complete Lower Cable
Installation
A. Attach one 3½-inch pulley to the Floating Pulley
Plates to the end with the single hole as shown
using
one 2-inch bolt
two washers
one locknut
Finger tighten.
B. Hang the pulley in the Floating Pulley Plates on
the Main Cable where it enters the Pulley Support
Tube.
C. Wrap the Lower Cable over one 3½-inch pulley and
attach the pulley to the Floating Pulley Plates in the
appropriate hole, using
one 2-inch bolt
two washers
one locknut
Avoid any twists in the Cable. Wrench tighten.
Note:
The Floating Pulley Plates have two holes
where the pulley can be installed. Generally,
you would use the upper hole. However, if you
purchased the Leg Press Option and are installing
it, use the lower hole.
D. Wrap the Lower Cable under one 4½-inch pulley
and attach the pulley between the two plates at
the base of the Main Upright using
one 2¼-inch bolt
two washers
one locknut
Finger tighten. Make sure that the Cable passes
between the pulley and the cable retainer pin.