IG-245-EN version 05; 13/02/2020
39
General Instructions
mb
.m
Installation
b.
Unscrew the two bolts that join the two halves of
the clamp.
Tool:
Phillips screwdriver.
Figure 5.26.
Disassembling the clamp's connecting bolts
c.
Separate the clamp to release the panel.
d.
Repeat the process for all clamps that hold the panel
to be taken down.
Proceed in reverse order to reassemble the perimeter fence.
5.8.4. Transformer secondary connection
The customer or installer is responsible for the cable input
to the
mb
.m transformer secondary.
Local electrical safety regulations must be taken into
account when accessing during the installation process in
order to complete the transformer secondary connections.
Remove the power supply in the primary and secondary
connections to the
mb
.m transformer substation.
Follow the procedure of the local utility company and
electrical safety regulations in order to de-energise
the
mb
.m
Follow the procedure described in section 5.8.3 if the
transformer's protection is to be removed.