STARTING 

 

WARNING:  Before  start  up  insert  wholly  turbolaters  into  the  smoke  tubes  ensuring  that  they  have 
been pushed inside for at least 100 mm. 

 

5.1  PRELIMINARY CHECKS 

Before starting the boiler, check that: 

The 

rating  plate

  specifications  and  power  supply  network  (electricity,  water,  gas  or  fuel  oil) 

specifications correspond; 

The burner 

power range

 is compatible with the power of the boiler; 

The boiler room also contains the instructions for the burner;  

The 

flue gas exhaust pipe

 is operating correctly;  

The 

air inlet supply

 is well dimensioned and free from any obstacle; 

The manhole, the smokebox and the burner plate are closed in order to provide a complete flue gas seal;  

The system is 

full of water

 and that any 

air pockets

 have therefore been eliminated;  

The 

anti-freeze

 protections are operative; 

The water 

circulation pumps

 are operating correctly.  

The expansion vessel and the safety valve(s) have been connected correctly  (with no interception) and 
are properly operating. 

-

 

Check the electrical parts and thermostat operation.

 

 

5.2  WATER TREATMENT 

The most common phenomena that occur in heating systems are: 

-  Scaling 

Scale obstructs heat transfer between the combustion gases and the water, causing an abnormal 
increase in the temperature of the metal and therefore reducing the life of the boiler.  

Scale  is  found  mostly  at  the  points  where  the  wall  temperature  is  highest  and  the  best  remedy,  at 
construction level, is to eliminate areas that overheat.  
Scale  creates  an  insulating  layer  which  reduces  the  thermal  transfer  of  the  generator,  affecting  system 
efficiency. This means that the heat produced by burning the fuel is not fully exploited and is lost to the flue. 

 
 
 

Scale diagram

  

 

Key 
%

  

% fuel not used 

mm 

mm of scale 

 
 
 
 
 
 

-  Corrosion on the water side 

Corrosion  of  the  metal  surfaces  of  the 
boiler on the water side is due to the passage of dissolved iron through its ions (Fe+). In this process the 
presence of dissolved gases and in particular of oxygen and carbon dioxide is very important. Corrosion 
often occurs with softened or demineralised water which has a more aggressive effect on iron (acid water 
with  Ph  <7):  in  these  cases,  although  the  system  is  protected  from  scaling,  it  is  not  protected  against 
corrosion and the water must be treated with corrosion inhibitors.  

 
 

5.3  FILLING THE SYSTEM 

The water must enter the system as slowly as possible and in a quantity proportional to the air bleeding 
capacity of the components involved. Filling times vary depending on the capacity and characteristics of the 
system but should never be less than 2 or 3 hours.  

In  the  case  of  a  system  with 

closed  expansion  vessel

,  water  must  be  let  in  until  the  pressure  gauge 

indicator reaches the static pressure value pre-set by the vessel.  
Heat the water to maximum temperature and never over 90°C. During this operation the air contained in the 
water  is  released  through  the  automatic  air  separators  or  through  manual  bleed  valves.  The  water 
discharged from the system with elimination of the air is made up by the automatic or manual filling valve.

 

 

Summary of Contents for SCP PLUS 3000

Page 1: ...TECHNICAL MANUAL The above picture is only for reference SCP PLUS THREE PASS WET BACK HOT WATER BOILER ...

Page 2: ...ions 3 2 2 Drawing 4 3 ACCESSORIES 5 3 1 THERMOSTATS 5 3 2 MANOMETER 5 3 3 THERMOMETER 5 4 INSTALLATION 6 4 1 BURNER 6 5 STARTING 7 5 1 PRELIMINARY CHECKS 7 5 2 WATER TREATMENT 7 5 3 FILLING THE SYSTEM 7 6 OPERATION 8 6 1 OPERATION CHECKS 8 6 2 CLEANING AND SERVICING 9 ...

Page 3: ...ion code Rated thermal output in kW Types of fuels that can be used Max operating pressure IMPORTANT This boiler has been designed to heat hot water at a temperature inferior to the boiling temperature at atmospheric pressure and must be connected to a heating plant and or a domestic hot water plant within the limits of its performance and output ...

Page 4: ...load 92 0 92 0 92 0 92 0 92 0 92 0 Efficiency 30 load 94 0 94 0 94 0 94 0 94 0 94 0 Gas flow rate G20 m h 345 403 472 575 690 805 Combustion and flue data Flue Gas Volume m min 130 5 152 2 178 3 217 4 260 9 304 4 Approx Flue Gas Temp ºC 181 181 182 181 181 181 Comb Chamber Resistance mbar 13 5 18 0 11 7 14 0 12 0 14 0 Water system Hydraulic Resistance 11k mbar 64 2 86 9 120 1 73 8 105 9 144 0 Hydr...

Page 5: ... safety pressure switch not supplied N1 Flow N2 Return N3 Fitting for instruments N4 System filling drainage N5 Connections for safety valves N6 Bulb wells N8 Inspection well N11 Fitting for level minimum probe SCP PLUS 3000 7000 NOTE drawing legend and data refer to standard models For specific models please refer to the provided accessory drawing ...

Page 6: ...te the second flame of the two stage burner The safety thermostat locks the burner at a fixed temperature value and sends out an alarm signal Restarting occurs only after the cause of the alarm has been removed and the system has be reset by operating the reset button on the switchboard 3 2 PRESSURE GAUGE The pressure gauge is Bourdon type consisting of a flat elliptical section metal tube bent to...

Page 7: ...Check that the boiler is fired by the correct type of fuel d Check that the fuel supply pressure is within the values specified on the burner rating plate e Check that the fuel supply system is sized for the maximum flow rate necessary for the boiler and that it is provided with all control and safety devices provided for by the regulations referred to above f Check that the boiler room vents are ...

Page 8: ...evel is to eliminate areas that overheat Scale creates an insulating layer which reduces the thermal transfer of the generator affecting system efficiency This means that the heat produced by burning the fuel is not fully exploited and is lost to the flue Scale diagram Key fuel not used mm mm of scale Corrosion on the water side Corrosion of the metal surfaces of the boiler on the water side is du...

Page 9: ...rature CO Gas 10 190 C 0 20 ppm Gas oil 13 195 C 10 80 ppm Heavy oil 13 5 200 C 50 150 ppm A diagram is provided in which the system efficiency is obtained according to the flue gas temperature the ambient temperature and the percentage of carbon dioxide CO2 Dispersions through the boiler casings are not considered Example Fuel used GAS OIL CO2 13 Ambient temperature 20 C Efficiency 91 4 Key Tf Fl...

Page 10: ... box while the burner is working Always wait few minutes after the burned has been switched off until the insulating parts are cooler 6 2 CLEANING AND SERVICING Close fuel supply and disconnect the electrical mains before starting any cleaning and servicing operations As economic running depends on cleaning of the exchange surfaces and regulation of the burner the following operations should be pe...

Page 11: ...10 ...

Page 12: ...t Street Halifax HX1 4DB Tel 01422 355651 Fax 01422 359636 The data reported are indicative only and are not binding Our company reserves the right to introduce alterations at any time as it deems fit and proper for the development of the product ...

Reviews: