4.4.3. Adjusting the ZERO
-
Necessary when a cell is replaced.
-
At least twice a year.
-
Connect a voltmeter to the two terminal posts provided for that purpose (MF and MES), as
shown below.
Be sure to be in pure atmosphere (without gas) (If not, inject air)
-
Adjust the ZERO (0 mV) with the potentiometer, item 1.Figure8
4.4.4. Checking the sensitivity
-
Necessary when a cell is replaced.
-
At least twice a year.
-
Prepare the calibration kit and secure the gas input pipe to the detector.
-
Adjust the flow rate of the reference gas
6
(1) to 60 l/h before injecting.
-
Allow to stabilize for at least 10 seconds.
-
Check that the alarm or alarms are triggered (as applicable
6
) and carry out the following
procedure.
6
The value of the reference gas must be higher than at least the first alarm threshold.
FIGURE 8
MV
Rep 2
Rep 1
Rep 3
Summary of Contents for SV 4B
Page 1: ...Surveyor 4B Part Number NPS4BGB Version C The Fixed Gas Detection People User Manual...
Page 2: ......
Page 6: ...6...
Page 8: ...8...
Page 20: ...20...
Page 22: ...22 VII EC DECLARATION OF CONFORMITY...
Page 23: ...23...