3. Commissioning
3.1. Fuses and switches
Switch/
fuse
Device
Q1
Main power
S2
Brine pump
F1
Compressor 1
F2
Compressor 2 (not in RE 35 or RE 42)
F3
Brine pump
F5
Condenser circuit pump
F6
Control system
F9
Desuperheater circulation pump (optional)
3.2. Prerequisites for commissioning
Make sure you are familiar with the control system and know how to change and save
settings etc. before you start commissioning the system.
It is recommended that Oilon expert does the commissioning.
Tasks to be completed before commissioning
● Ground circuit connected, filled and vented.
● Heating circuit connected, filled and vented.
● Buffer tank and heating system filled and vented.
● All necessary feed cables and sensors connected.
3.3. Commissioning the system
Before starting commissioning, check that all installation tasks described in the
previous chapters have been completed.
1. Make sure all switches (
Q1
,
F1
–
F9
) are in position 0.
2. Turn on main switch
Q1
to position 1 and turn on switch
F6
.
It takes a while for control system to start up.
Because the motor protective switch(es)
F1
(/
F2
) is still off, the control system
displays an error on the screen. You can ignore the error at this point.
3. Set the heat pump basic settings.
a. Set the language, date, and time.
b. Set the heating curves and other optional settings as described in the following
sections.
4. Turn on switches
F3
and
F5
. If the desuperheater is in use, also turn on switch
F9
.
Summary of Contents for RE 35
Page 2: ......
Page 58: ...56 67 RE01 1445EN Wilo Stratos Para 25 1 12 WSP01 ver 1...
Page 59: ...RE01 1445EN 57 67 Wilo Stratos 40 1 12 WSP02a ver 1 WSP02b ver 1...
Page 60: ...58 67 RE01 1445EN Wilo IPL 40 115 0 55 2 WIPL03 ver 1...
Page 61: ...RE01 1445EN 59 67 Wilo IPL 50 115 0 75 2 WIPL02 ver 1...
Page 62: ...60 67 RE01 1445EN Wilo IPL 50 120 1 5 2 and Wilo IPL 50 130 2 2 2 WIPL01 ver 1...
Page 63: ...RE01 1445EN 61 67 Wilo Stratos Para 25 1 7 WSP03 ver 1...
Page 70: ...68 67 RE01 1445EN...
Page 71: ......