16
Installation
System Installation and Initialization
Installation and initialization of the system require attention to the normal mechanical, power, and
thermal precautions for rack-mounted equipment.
The installation procedure for the system involves the following phases:
Step
Procedure
See
1
Follow the safety warnings
2
Pay attention to the air flow consideration within
the system and rack
3
Make sure that none of the package contents is
missing or damaged
4
Mount the system into a rack enclosure
5
Power on the system
6
Perform system bring-up
7
[Optional] FRU replacements
Safety Warnings
Prior to the installation, please review the
. Note that some warnings may not apply
to all models.
The rack mounting holes conform to the EIA-310 standard for 19-inch racks. Take
precautions to guarantee proper ventilation in order to maintain good airflow at ambient
temperature.
Unless otherwise specified, NVIDIA products are designed to work in an environmentally
controlled data center with low levels of gaseous and dust (particulate) contamination.
The operation environment should meet severity level G1 as per ISA 71.04 for gaseous
contamination and ISO 14644-1 class 8 for cleanliness level.
Summary of Contents for SN2010
Page 12: ...12 SN2700 SN2740 SN2410 SN2100 SN2010 Rear View...
Page 66: ...66 Port LEDs System Port LEDs SN2700 SN2740 SN2410 QSFP28 SFP28 SN2010 QSFP SFP...
Page 69: ...69 SN2410 Inventory Information Illustration SN2100 Pull out Tab SN2010 Pull out Tab...
Page 70: ...70 SN2201 Pull out Tab...
Page 88: ...88...