NuAire XBC75-V Series Installation Manual Download Page 8

8

21. 01. 21. Document Number  671661

Nuaire | Western Industrial Estate | Caerphilly | CF83 1NA | nuaire.co.uk

XBC 75 & 85 (ES / BC Control) 

Installation Manual

If the control is rotated to aid connection of cables, please ensure that 
sufficient flexibility is provided in the final connection run.

To avoid conflict with the unit access panels, it is recommended 
that electrical and plumbing service connections to the unit are run 
at 90 degrees to the main air flow axis.

Control circuit connections must be segregated (i.e. routed separately) 
from power connections.

The unit rating label shows the maximum electrical load of the 
equipment. Connections to the unit may include single phase supply 
connections, and a variety of control circuits.

Only the prepared apertures in the unit casing may be used for cable 
entry. Do not drill or cut the unit casing for this purpose.

The equipment must be earthed and earth-bonded. Means of local 
isolation for maintenance purposes are generally required (by others). 
Ensure that all mains connections are isolated.

Heat recovery components and modules that incorporate cooling 
coils may produce condensation during use. An insulated drip tray and 
condensate pump is provided.  The drain connection must be connected 
to a suitable drainage point (Figures 11 & 12).

6.1 Condensate Pump

The condensate pump incorporates an alarm function. If the water 
level in the condensate tray exceeds a maximum level (for example, as 
a result of the discharge tube becoming blocked or frozen), the alarm 
contact will open. This contact is internally connected to the heat 
exchanger bypass actuator, and the unit will automatically be placed 
into bypass mode, preventing further condensate production. Unit 
operation will otherwise be unaffected.

Maximum flow rate = 12 l/h 
Maximum head = 20m Vertical, 100m Horizontal 
Pipe Connection size (Condensate) XBOXER XBC = 8 mm

7.0 COMMISSIONING

Not all of the components listed here are necessarily included with 
the equipment supplied. 

10 

Customer Connections (Control Side of Horizontal Unit)

LPHW or electric heater

supply connections

Control box

Access to condensate

tray and pump

Condensate drain 

connection Ø 8mm push-fit

7.1 Filters

Remove filter access panels (observe and note airflow direction labels), 
inspect filters for contamination with construction debris, replace as 
necessary. Replace access panels. 

Filter pressure drops will depend on actual flow rate and condition. 
Observe and record filter pressure drops after performance 
commissioning. Typically, filter “dirty” condition occurs when the initial 
filter “clean” readings have been increased by 125Pa.

If filter manometers, pressure switches or indicators have been fitted, 
they should be set or adjusted to reflect the commissioned system 
operation.

11 

Customer Connections (Control Side of Vertical Unit)

LPHW or electric heater

supply connections

Control box

Access to condensate

tray and pump

Condensate drain 
connection 
Ø 8mm push-fit

Fixed panel for

customer connections

7.2 Heating Coils LPHW

Observe the Flow and Return connection labels on the unit. Drain and 
bleed valves are located on the coil. Other valves may be required in the 
system pipe-work depending on the installation (by others).

Where the wet system is at risk of frost damage, the addition of a 
proprietary anti-freeze solution to the water is recommended. Note 
that any frost protection offered by the unit’s integral control system 
will not operate if the power supply to the unit is interrupted.

Ecosmart frost protection is activated on any Ecosmart unit fitted with 
LPHW heating, when the outlet air temperature is 4ºC or below. The 
unit reacts by shutting down the fan to prevent a ‘wind chill’ effect 
reducing the temperature to a point whereby the coil could freeze 
and burst. The unit will also drive open the LPHW valve to a fully open 
position to allow full water flow through the coil and the main PCB 
will close the ‘Heat demand’ contacts. These contacts could be used to 
send a signal to activate the boiler and/or valve to open to provide heat 
if not already doing so.

Piped connections should be made to the unit using appropriate 
techniques, and all pipework must be independently supported. No hot 
work is permitted within one metre of the unit.

Ensure that installed pipework runs do not prevent or restrict access to 
the unit at any point.

The completed installation (including the connections within the unit, 
as these may be disturbed during installation) shall be pressure tested 
to the project engineer’s specification (

This is a condition of the unit 

warranty). 

7.3 Electric Heaters

Heater Capacity:   XBC75 – 3ph, 12Kw 
 

 

XBC85 – 3ph, 18Kw

The Electric Heater requires a 3ph supply which is independent from 
the main unit supply. Connections to be made through the low level 
fixed panel. The Electric Heater may be withdrawn to allow access to 
the Heater Controller without the need for wiring to be disconnected 
(Ensure the mains supply is isolated before removing any access panels 
and any adjustments are made to the Heater Controller).

Summary of Contents for XBC75-V Series

Page 1: ...TATING PARTS This unit contains fast moving rotational parts which may start automatically It is the sole responsibility of the installer to adequately guard these components REFER TO INSTRUCTION MANU...

Page 2: ...5 Attenuator Length 900 900mm 6 Unit Roof No Suffix Standard Unit No Roof WP Twin Pitched Roof Factory Fitted 3 0 DELIVERY 3 1 Receiving Equipment All equipment is inspected prior to despatch and lea...

Page 3: ...nit Dimensions mm and Weights kg Unit Code Unit Dimensions mm Control Dimensions mm Unit Weights Packed Weights A B C J K M E F G kg kg XBC75 H 2800 2126 876 940 740 940 250 730 800 720 902 XBC85 H 28...

Page 4: ...Horizontal XBC75 Units 2000 1001 600 117 4 3 4 Dampers Ref No XBC Ancillary Code Description Dimensions mm Weight kg Width Height Length 4 XBC75 H MD24V Motorised dampers 24V for Horizontal XBC75 Eco...

Page 5: ...ns mm and Weights kg Unit Code Unit Dimensions mm Control Dimensions mm Unit Weights Packed Weights A B C J F H W D kg kg XBC75 H 2500 954 1416 610 894 60 954 2500 630 730 XBC85 H 3000 1000 1676 940 7...

Page 6: ...000 1741 600 107 4 5 4 Dampers Ref No XBC Ancillary Code Description Dimensions mm Weight kg Width Height Length 4 XBC75 V MD24V Motorised dampers 24V for Vertical XBC75 Ecosmart model ES Units 620 56...

Page 7: ...Battery 5 2 Vertical Units e g XBC75 V XBC85 V 8 Vertical Unit Access All access panels are located on one side of the fan unit Note Unit must be isolated before panels are removed 9 Vertical Unit Ove...

Page 8: ...ondition Observe and record filter pressure drops after performance commissioning Typically filter dirty condition occurs when the initial filter clean readings have been increased by 125Pa If filter...

Page 9: ...rnal nylon aluminium blade interconnection linkage Fitted with Belimo SM230A S drive open drive close actuator complete with switch Motorised damper wiring will require connection on site and possible...

Page 10: ...for Ecosmart Devices Max SL run on 0 Test Link Wire 1 Trickle ES CO2 Connection BMS Input Signal 0V 0 10V Ecosmart Pwr Standby Fan 1 Heating Fan 2 Cooling Fault TX RX Frost Extract N E L SL DP CL N R...

Page 11: ...st Link wire see note Trickle 1 ES CO2 BMS Connection Input Signal 0 10V 0V Ecosmart Pwr Standby Fan 1 Heating Fan 2 Cooling Fault TX Frost RX Extract N E L SL DP CL N RET Run Fault Damper Connections...

Page 12: ...t 80 C maximum The fans should remain running for at least 4 minutes after the electric element is turned off to ensure the unit does not overheat Do not wire power supply directly into the heating el...

Page 13: ...required local to heater Min NET Connections for Ecosmart Devices NET Connections for Ecosmart Devices Max o n SL run Test Link wire see note 0 1 Trickle ES CO2 BMS Connection Input Signal 0 10V 0V Ec...

Page 14: ...nt knob is located in the control pack and must be set to the desired air off temperature MIN Minimum speed adjustment MAX Maximum speed adjustment SL Run on Switched Live Run On Timer TRICKLE adjustm...

Page 15: ...ther paper components can be largely recycled or fully processed in energy from waste centres Remaining Items can be further segregated and processed in accordance with the zero waste hierarchy Please...

Page 16: ...the weather and steps taken to prevent ingress of contaminants 4 0 OPERATIONAL LIMITS 4 1 It is important that the specified operational limits for the equipment are adhered to e g operational air te...

Reviews: