NOVENCO FALKINN ACN Installation And Maintenance Download Page 4

4

6.3 Impeller

From the factory the impeller is supplied 
with the blades adjusted to the pitch cor-
responding to the desired operating 
point (pressure and air flow) at the fan 
speed in question. To ensure vibration 
free operation the impeller has been 
carefully balanced in this position.
Vibrations occurring during operation 
will normally be due to accumulations of 
dust or dirt on the hub and blades, and 
will disappear after cleaning. Should this 
not be the case, expert assistance should 
be called in immediately, as continued 
vibrations will shorten the life of the mo-
tor bearings.

6.4 Motor

The motor normally only requires main-
tenance of the bearings as indicated in 
the maintenance instructions for electric 
motors.

6.5 Dismounting of motor for 

types
ACN-smoke (see fig. 5)

Prior to commencing the work, switch 
off the current and disconnect the motor 
cable. Next, dismount any ducts on the 
fan inlet and outlet sides. Remove the 
impeller centre screw (see item 01), cen-

tre disc (see item 02) and hub cover (see 
item 03).
Dismount the impeller by means of a 
puller fastened in the 2 threaded holes of 
the hub boss/threaded holes for puller 
(see item 05).
Detach the motor by loosening the 
screws in the motor shell (see item 06). 
Now the motor (see item 11) and motor 
flange (see item 10) can be removed.
In dismounting and disassembling the 
fan be careful not to expose the individu-
al parts to shocks etc. likely to damage 
the motor bearings or other fan compo-
nents.

6.6  Mounting of motor for types 

ACN-smoke (see fig. 5)

After servicing remount the motor, take 
care that the motor flange (item 10) is cor-
rectly located and that the motor shaft is 
concentrically placed in the fan casing 
before tightening the bolts (item 06).
Mount the impeller (item 04) on the mo-
tor shaft by means of a tool fastened in 
the threaded hole of the motor shaft.
Fix the impeller hub to rest against the 
motor shaft collar.
Check that the blade clearance of the im-
peller is the same throughout the circum-
ference of the casing. If that is not the 

case, adjust the motor location in the sus-
pension arrangement.
Now mount centre screw (item 01), cen-
tre disc (item 02), and hub cover (item 
03). Replace lock washers/lock nuts dur-
ing fan assembly. Finally connect motor 
cable (item 13) in terminal box (item 12) 
and ducts, if any.
To start the fan follow the procedure de-
scribed in section 5. Start of operation.

6.7 Blade pitch adjustment

The blade pitch has been adjusted in the 
factory with a special tool (mounting fix-
ture) to deliver the performance required 
by the customer/order on delivery.
If the fan performance is required to be 
changed it is possible to change the blade 
pitch. It requires knowledge of the motor 
load and the max. permissible blade 
pitch on the graph as related to the motor 
rating (in case of blade pitch increase).
Contact Novenco before any such ad-
justment of the blade pitch. Novenco can 
supply special tools for blade pitch ad-
justment and instructions for impeller 
balancing. The brochure “Blade Angle 
Tool” is available on request.

Figure 5. Dismounting/mounting of axial flow fan 

Summary of Contents for FALKINN ACN

Page 1: ...supplied with approval number class category are also men tioned as well as test standard applied EN 12101 3 Fan pressure air quantity output and maximum speed per minute The fan is also provided with a motor nameplate with relevant motor data in cluding insulation class of the motor 2 2 Weight The total weights shown in table 1 apply to axial flow fan type ACN smoke The totalweightisdeterminedont...

Page 2: ...uspended in the fan casing flanges or in special carriers The carriers must not hamper the free in let and outlet of air When the fan has been finally secured makesurethattheimpellerrotatesfreely in the casing If the motor is provided with drain holes for condensed water the fan must be ori ented so that the holes turn downwards lowest point Generally it is of the utmost importance for the perform...

Page 3: ...med by the person responsible for the operation of the system and the documentation must be kept and produced whenever asked for Prior to start of operation check that the fan and duct connections are clean and free from tools and foreign substances Also check that the electric connections meet the prescribed requirements that any wire guard fitted on the fan inlet or outlet side is correctly moun...

Page 4: ...r bearings or other fan compo nents 6 6 Mounting of motor for types ACN smoke see fig 5 After servicing remount the motor take care that the motor flange item 10 is cor rectly located and that the motor shaft is concentrically placed in the fan casing before tightening the bolts item 06 Mount the impeller item 04 on the mo tor shaft by means of a tool fastened in the threaded hole of the motor sha...

Page 5: ...ectricity supply Cleaning inside with pressure air outside with water Itisrecommendedtoenterallvaluesand observations in a log 8 Sound The sound generation of the fans de pends on installation and operating con ditions which means that no general da ta of the sound generation can be given Reference is made to our catalogues or computer programs for calculation of the specific sound generation 9 At...

Reviews: