16
1-5 ELECTRICAL CONNECTIONS:
INSTALLATION & SETUP
NOTE: All electrical connections should be made by a qualified electrician.
Before making any electrical connections, insure that the voltage listed on the electrical box and circuit
breakers matches that of your facility (i.e. 230V - 3 Phase -40 Amp).
Refer to Figure 1-3 for the standard electrical connections. Norfield recommends that you have a main
disconnect switch for the input source near the machine. This switch is usually wall mounted near the
machine in a position convenient to the operator (or maintenance person) for safety reasons.
After power has been connected, check the rotation of the Lock Drill Motor. Correct rotation has the mo
-
tor turning COUNTER-CLOCKWISE when viewed from the front of the machine. If the rotation is not
correct, have the electrician reverse the two outside leads on the three phase input.
THREE PHASE CONNECTION - CON-
NECT HIGHEST VOLTAGE LEG TO
CENTER LUG
MAIN ELECTRICAL
PANEL
FIGURE 1-3
1-4 AIR SUPPLY AND CONNECTIONS:
The Magnum requires 2.2 CFM of clean, dry air @ 90 PSI (8.5 CFM if air screwdriver and pre-drill is used)
for proper operation. The air supply is connected to the machine at the filter-regulator-lubricator (FRL)
unit located on the outfeed end of the main frame (FIG 1-2). The supply line should be 1/2” minimum if
the length of the run is 75’ or less. For runs between 100’ and 300’, a 3/4” supply line is recommended.
For convenience, a quick disconnect at the connection point and an air shut-off valve near the machine is
GROUND
NEUTRAL
SINGLE PHASE INPUT
THREE PHASE INPUT