4.5
Testing Low Voltage Power Supply.
Identify the test GND, 5V and HV test points as shown below.
Plug in the power supply, and then test using a DC voltmeter:
Touch the black probe on the GND test point and the red probe on
the 5V test point. The voltage should measure between 4.8 and 5.2
Volts. If not, disconnect power and check your work. Do not
proceed with the assembly until the error is corrected. Once the
test is completed, disconnect the power.
4.6
High Voltage Generator Components.
6 Way female header
28 Way IC socket for IC2
R1 (6.8 KΩ)
VR1 (1 KΩ Potentiometer)
HV Module
Start by soldering the 6 way male header to the HV Module.