21
INSPECTION AFTER INSTALLATION
PROHIBITED
!
• Check the following immediately after installation
DANGER
Procedures to be carried out before the power source switch is turned "ON".
1. The load chain must always be free from twists. When the hoist lifts on two or more falls of load
chain, twist can arise from the bottom hook being accidentally turned over through the load chain.
2. While the hoist is not under a load, lubricate the whole length of the load chain with machine oil,
and be sure to give the contact points between the links extra coatings.
Procedures to be carried out after the power source switch is turned "ON".
1. The hoist is equipped with a negative phase protector. When the hoist does not function when the
pendant push buttons are depressed, the negative phase protector is functioning. lf this happens,
interchange the position of two wires of power source cable.
2. As shown in the lower drawing, a reverse connection can be corrected by interchanging two (wires
"S" and "T ") of the three wires of the power source cable.
When "Power source connection (a)" is a reverse connection, the reverse connection can be
corrected by interchanging wires " S " and " T " as shown in " Power source cable connection (b) " .
Extra coating of machine
oil at contact points
Hoist with two falls of
load chain
Power source switch
Power source switch
Power source cable connection
(a)
Power source cable connection
(b)