PREPARING THE INSTALLATION LOCATION
Minimum Tools Needed
Locate the desired installation location (no lower than 18” inches from the ceiling). Using
a stud finder, locate the studs on either side of the center point, and mark them with
vertical lines.
Using a level and a pencil, mark a horizontal line on the wall between the two studs, no
less than 1 1/2” and no more than 18” from the ceiling.
Using a ruler or measuring tape, measure 16” down, and mark another horizontal line
parallel to the first one.
Using a saw, cut along the uppermost horizontal line until your saw reaches the stud.
Turn the saw around, inserting it into the cut you have just made, and cut toward the
opposite stud so that you have a clean horizontal cut between the two studs. Be careful
not to cut into the studs themselves.
Now make the second horizontal cut from stud to stud on the line 16” below the first cut.
Once the horizontal lines have been cut, make vertical cuts using the inside edge of the
studs as a guide. Once you have made both vertical cuts, you should have a rectangular
hole in the sheetrock. Now you have to make the same hole on the other side of the wall.
Since you already have one hole, this is an easy process. Using a nail, mark all four corners
of the first hole by making nail holes through the sheetrock. Then on the other side of the
wall, connect the holes with a pencil mark and cut.
Once the horizontal lines have been cut, make vertical cuts using the inside edge of the
studs as a guide. Once you have made both vertical cuts, you should have a rectangular
hole in the sheetrock. Now you have to make the same hole on the other side of the wall.
Since you already have one hole, this is an easy process. Using a nail, mark all four corners
of the first hole by making nail holes through the sheetrock. Then on the other side of the
wall, connect the holes with a pencil mark and cut.
Sheetrock alone cannot support the weight of a cooling system. Therefore, it is necessary
to frame the hole that you have just cut with upper and lower supports. These supports
also provide solid material for the mounting bracket screws.
Using two 2x4s at 14.5” in length and eight 6d nails, secure the upper and lower supports
to the right and left studs, just inside the sheetrock. Make sure that the internal height
remains at 16” so that the system will fit snugly through the framed cut-out.
Hammer
Saw
Screwdriver
Level
Summary of Contents for 3000
Page 1: ......
Page 15: ...Page 13 VERSION 2 CONTROLLER WIRING SCHEMATIC Cond Fan Compressor Cond Fan Evap Fan Evap Fan...
Page 18: ...Page 16 WE 081313 VERSION 1 CONTROLLER WIRING SCHEMATIC...
Page 25: ...Page 23...
Page 26: ...Wine Enthusiast Companies 333 North Bedford Rd Mt Kisco NY 10549 www wineenthusiast com...