6
CO mg/m3 @ 13% 02: 930
NoX mg/m3 @ 13% 02: 112
2.0 Installation introduction
2.1 Unpacking the stove
After removing the outer packaging, remove the combustion chamber from the wooden pallet and
place it gently on its back. The cardboard packaging can be placed underneath to prevent marring.
Remove the leg pack from the stove if not assembled at manufacture, bolt each leg securely to the
underside of the base on the combustion chamber, using the bolts provided (found inside the
stove). Note: There are lower bolts supplied for fitment into holes in the base of each leg, these are
adjustable to allow level adjustment of stove to uneven surfaces.
We recommend that two people perform the assembly and installation procedure.
2.2 Installing this stove
The stove and chimney installations
MUST
comply with all current National and Local Building
Regulations and any Rules in Force including current issues of British Standard BS 8303 code of
practice for installation of domestic heating and cooking appliances burning solid mineral fuel and
British Standards BS EN 15287-1:2007 design, installation and commissioning of chimneys; your
approved dealer or your local building control officer can advise regarding this. Ultimately, it is
you and your installer who is responsible to ensure that the installation complies with all relevant
regulations and any rules in force.
For installations within England and Wales also refer to Document J that gives guidance on
complying with the Building Regulations.
2.2.1 Tertiary air control.
The Tertiary air intake is a standard part for the Rydal 5 SE stove, there is no control to the tertiary
air intake as it is set at 100% open at manufacture.
2.2.2 Assembling the baffle and removeable internal parts.
See figures 1.1 to 1.10
All stove internal parts are assembled at manufacture, however with movements and handling
during stove delivery it is possible that some or all of the located parts inside the stove may have
moved, therefore it is important to check all these parts for correct position and fitment after the
stove is located. Check the baffle and all other parts are located into correct positions including
side cheeks, grate assemblies, banking bar and ash pan. Before lighting the stove for the first time,
confirm the baffle and all parts are in correct location.