16
6 Installing the Pit Version
This section describes storage and unpacking instructions, preliminary tests, tools,
materials, site selection, and pit installation of theE-Coder)R900
i
version MIU.
Prior to Installation
Storage
Upon receipt, inspect shipping containers for damage and inspect the contents of
any damaged cartons prior to storage.
Once the inspection is complete, store the cartons in a clean, dry environment.
Keep in mind that the E-Coder)R900
i
pit version has an internal battery. Storage
for more than one year may affect product life. Be sure to use a first-in first-out
inventory control system. See “Environmental Conditions” on page 3. The unit
should not be transmitting until the box is opened and the unit is exposed to a light
source.
Unpacking
As with all precision electronic instruments, the E-Coder)R900
i
MIU should be
handled carefully; however, no additional special handling is required.
After unpacking the MIU, inspect it for damage. If the MIU appears to be damaged
or proves to be defective upon installation, notify your Neptune Sales Representa-
tive. If one or more items requires reshipment, use the original cardboard box and
packing material.
Figure 6 E-Coder)R900
i
Pit Installation
Summary of Contents for E-Coder)R900i
Page 3: ......
Page 4: ...E Coder R900i Installation and Maintenance Guide ...
Page 7: ......
Page 11: ...viii E Coder R900i Basement and Pit Installation and Maintenance Guide Notes Figures ...
Page 13: ...x E Coder R900i Basement and Pit Installation and Maintenance Guide Notes Tables ...
Page 43: ...Notes 4 E Coder R900i Basement and Pit Installation and Maintenance Guide ...
Page 44: ......