Installing the Basement Version
E-Coder)R900
i
Basement and Pit Installation and Maintenance Guide
13
Testing the E-Coder)R900
i
Basement Installation
After the MIU has been installed, follow these steps to verify that
the MIU is working properly.
1
Power up the handheld unit (HHU) test device to start the
testing program provided.
2
When the E-Coder)R900
i
is installed correctly, its MIU ID#
and a meter-reading appears on the HHU’s display within one
minute. Verify that this is the correct meter reading by com-
paring it to the meter’s dial.
3
If a meter reading does not appear on the HHU’s display or the
meter reading in the HHU’s display is not the same as the read-
ing on the meter’s dial:
•
Reactivate the MIU by using a flashlight to activate the
photo sensor light.
•
Verify the battery is connected.
•
Test the installation again (repeat steps 1 and 2).
Completing the E-Coder)R900
i
Basement Installation
1
Read the MIU one more time before leaving the site to ensure
MIU is transmitting.
2
Make sure the appropriate ID# on the MIU has been assigned
to the meter setting.
To avoid RF signal saturation of the HHU, position the receiver at least 2
to 3 feet from the MIU. In a densely saturated area, removing the antenna
from the handheld can assist with readings.
A register reading of 8 digits will be returned.
The light sensor is located under a small recess near the center of the dial
plate. This recess is denoted by a flashlight symbol on the dial plate.
All tags are provided to aid in the elimination of transcription errors.
Summary of Contents for E-Coder)R900i
Page 3: ......
Page 4: ...E Coder R900i Installation and Maintenance Guide ...
Page 7: ......
Page 11: ...viii E Coder R900i Basement and Pit Installation and Maintenance Guide Notes Figures ...
Page 13: ...x E Coder R900i Basement and Pit Installation and Maintenance Guide Notes Tables ...
Page 43: ...Notes 4 E Coder R900i Basement and Pit Installation and Maintenance Guide ...
Page 44: ......