4.1.3
Adjusting Stud Stop Assembly
1
Loosen the set screw.
2
Adjust the stud stop (Figure 4.1 Chuck and Stop Assembly) so that the stud being welded
extends 4 mm beyond the chuck.
3
Tighten set screw.
NOTE: For long studs, use maximum chuck depth. The chuck is assembled as shown and inserted
into the chuck adaptor. The chuck must be in firm contact with the stud stop while tightening the
chuck nut.
4.2
Setting Up Foot and Leg Assembly
The NCD+ guns come supplied with a foot and spark shield (Figure 4.2 Foot & Leg Assembly). The
foot is installed on the end of the legs. Alignment of the foot is important. The chuck should be
located in the center of the spark shield. To install the foot, unscrew the leg screws and place them
through the holes in the foot. Reattach the leg screws to the legs. Maintain concentricity between
the chuck and spark shield.
Figure 4.2 Foot & Leg Assembly