background image

9

BAFFLE PLATE LOCATION 

To clean your flue system the baffle plate will need to be removed. 

Before continuing ensure the fire is completely extinguished. 

1) Lift baffle up from the rear and slide forward out through the door. You will 

    need to lift the rear lip of the baffle plate over the front and rear mounting rods. 

2) After cleaning the flue system simply reverse the procedure and replace your

    baffle. 

3) Do not light the fire while the baffle is removed as this could cause a serious 

    house fire.

      

BAFFLE PLATE

GENERAL OPERATION 

Once the heater has been burning on high for approximately 20 to 30 minutes it

will have reached operating temperature.  You may now slow the burn down by 

adjusting the air slide into the closed position.  Turn the fan on to the preferred

speed setting. 

When adding wood, open the air slide fully, wait a few seconds, then open the

door slowly.  After re-loading, leave air slide open, on high for 15 - 20 mins to

allow new fuel to catch freely and entirely. 

Then re-adjust the air slide to desired setting for maximum efficiency.  If the fire

is too small, refuelling first with kindling is advised. 

OVERNIGHT BURN

An overnight burn can be achieved by following these steps an hour before 

retiring: 

1) Open air slide fully

2) Load with large pieces of dry wood

3) When all wood is burning, slowly move the air slide to low position. 

4) Turn fan to OFF position. 

NOTE: This procedure can be done at any time, for example, in the morning so

that the fire is still going later that day.         

Summary of Contents for FS 800

Page 1: ...ing Instructions FS 800 FS 500 IS 800 IS 500 Pecan Engineering Pty Ltd 13 Acorn Road DRY CREEK SA 5094 Ph 08 8349 8332 Fax 08 8260 6643 www nectre com email info pecan eng com au Toll Free 1800 636 30...

Page 2: ......

Page 3: ...ONS OF HEATERS DOOR HANDLE ADJUSTMENT DOOR GLASS DOOR GASKET FIREBRICKS LIGHTING YOUR FIRE INITIAL OPERATING PERIOD GENERAL OPERATION OVERNIGHT BURN BAFFLE PLATE LOCATION FAN SERVICE CLEANING THE FIRE...

Page 4: ...rpretation of AS NZS 2918 2001 WARNING The heater must no be operated without the floor protector installed as heat radiation from the glass door may burn floor surfaces WARNING DO NOT BURN FLAMMABLE...

Page 5: ...than 300mm to the sides and 600mm above the hot air outlet without adequate heat shielding in terms on clause 3 4 2 AS NZS 2918 2001 FLOOR PROTECTOR Refer to AS NZS 2918 2001 Clause 2 2 3 3 1 3 3 2 a...

Page 6: ...ibles as shown below Currently for installation with an Australian Standard Double Cased flue kit with a full length half radius perforated mesh flue shield OUTER CASING NO LESS THAN 25MM CLEARANCE TO...

Page 7: ...TING PERFORMANCE MAY REDUCE AS A RESULT OF VAULTED CEILINGS DRAFTS LARGE GLASSED AREAS OR POOR INSULATION Y X Z Z B B A A MODEL X Y Z B MODEL HEIGHT WIDTH DEPTH REAR OF HEATER TO FLUE CENTRE IS500 Fas...

Page 8: ...OR GLASS Inspect door glass regularly for cracks and breaks If a crack is found extinguish fire immediately and replace glass Contact your dealer for replacement glass If your glass becomes stained or...

Page 9: ...n air slide fully 5 Light several parts of the newspapers 6 Close the door to avoid smoke spillage Do not close latch this will allow extra air into the firebox and helps create a draft After approxim...

Page 10: ...e open on high for 15 20 mins to allow new fuel to catch freely and entirely Then re adjust the air slide to desired setting for maximum efficiency If the fire is too small refuelling first with kindl...

Page 11: ...Lift baffle up from the rear and slide forward out through the door You will need to lift the rear lip of the baffle plate over the front and rear mounting rods 2 After cleaning the flue system simpl...

Page 12: ...ot to damage the blades 3 Plug in power and turn on CLEANING THE FIREBOX Ash should be cleared or removed when build up reaches the level of the door opening To clean use a metal fireplace shovel maki...

Page 13: ...ctric fans are only warranted against failure to operate for one year Under the terms of this warranty Pecan Engineering Pty Ltd assumes no reponsibility for the labour costs involved in removing or r...

Page 14: ...5mm 3 Baffle Plate 800 Series 590mm x 288mm x 8mm 500 Series 490mm x 248mm x 8mm 4 Door Rope 800 Series 1900mm x 16 mm Round 500 Series 1300mm x 16 mm Round 5 Glass Rope 800 Series 1840mm x 19mm x 3m...

Page 15: ......

Page 16: ...14...

Reviews: