Installation 

Mount the server to a rack in the following procedure. 

 

Important  Always install the server with three or more persons. 

 

1. Push the server into rack, and secure it with screws on left and right sides. 

 

 

Removal

 

Remove the server from the rack in the following procedure 

1.  Refer to Chapter 2 (1.3 Overview of Installation and Removal) in 

User

s Guide

 for preparations. 

 
 

2.  Make sure that the server is turned off and then disconnect the power cord or all interface cables from the 

server. 

3.  Remove screws from front left and right sides of server, and take out the server from rack gently and 

carefully. 

 

 

4.  Hold the server firmly and remove it from the rack. 

 

Important  While more than three persons are supporting the bottom part of the server, 

slowly pull out the server.   

Do not apply load on the server from top when it is being pulled out. Doing so 
cause the server to drop.   

 
 

Removing Rails 

Remove rails from the rack in reverse order of installation steps. 

 

Important

At least three persons are required to remove the server from rack. 

Important

Be careful not to get your fingers caught in the rails or lever. 

Summary of Contents for N8141-62F

Page 1: ...d or damage to the machine parts around the device Unplug the power plug Make sure to unplug the power plug from the electrical outlet and unplug the cables connected to external devices from the machine before installing or removing the product Touching the device of the NEC Express server with its power plug connected to a power source may cause an electric shock even if the NEC Express server i...

Page 2: ...ndling Guide 1 This guide Notes for Use Please be sure to observe the following notes after unpacking the product Do not put this product in a dusty place a place where sulfur steam exists in the air or a place where liquid such as water may splash onto it Do not put the product near strong magnetic sources Transfer to a Third Party When transferring or selling the product to a third party make su...

Page 3: ... server by a single person or two persons Do not install the server so that the load may be concentrated on a specific point Do not install any components only by a single person Confirm that hinge pins of the door are completely secured in place Do not pull out the server from the rack when the rack is unstable Do not leave more than one device being pulled out from the rack Do not provide the wi...

Page 4: ...s Use only under the specified environment CAUTION Be sure to observe the following precautions to use the server safely Failure to observe the precautions may cause burns injury and property damage For details refer to Safety precautions in Precautions for Use Do not drop Do not leave the server being pulled out Do not install with the cover removed Do not get your fingers caught Preparation Chec...

Page 5: ...The height of rails mounted on left and right sides must be level Important Confirm that the rails are securely locked so that they will not fall off Tips Although the rail assembly may be somewhat unsteady it is not defective Installing Removing the Server CAUTION Be sure to observe the following precautions to use the server safely Failure to observe the precautions may cause burns injury and pr...

Page 6: ...ower cord or all interface cables from the server 3 Remove screws from front left and right sides of server and take out the server from rack gently and carefully 4 Hold the server firmly and remove it from the rack Important While more than three persons are supporting the bottom part of the server slowly pull out the server Do not apply load on the server from top when it is being pulled out Doi...

Page 7: ...stall and lock the lever 2 Server Node Right Installation A push the lock to right side B pull the lever upside C install and lock the lever Tips Refer to user s guide and maintenance guide to install CPU DIMM HDD PCI card Important Pay attention to touch server node with the right inside wall of chassis when installing Important Pay attention to touch server node with the left inside wall of chas...

Page 8: ...er of enclosure Slot number on enclosure is as following Installing order is slot1 slot2 slot3 slot4 Blank panel installation Install blank panel on the slot that not installed server node N8141 61F Blank Panel Slot1 Slot2 Slot3 Slot4 ...

Page 9: ...LED on another power supply unit goes on amber When another power cord is connected AC POWER LEDs on both power supply units turn on green 2 Press the POWER switch at the front of the server node The POWER LED is turned on green and after a while the logo appears on the display M NMI Important Refer to user s guide and maintenance guide for error message in display or STATUS LED AC Power LED POWER...

Page 10: ... Insert the attached SDR UPDATE TOOL CD ROM in the optical disk drive of the servernode 3 After the CD ROM is inserted reset the server by pressing Ctrl Alt Del keys or turn off on the power to reboot the server 4 The system starts from the CD ROM and the SDR PIA setup starts automatically 2 to 3 minutes is required to complete the setup Be sure not to turn off the power during the setup When the ...

Page 11: ...856 129811 101 00 11 11 Protection form N8141 62F Module Enclosure Installation and Handling Guide ...

Reviews: